DC BLOX Atlanta East data center (Farmer Road)
Also called: DC Blox ATL East
DC BLOX plans three data center buildings, about 1 million square feet, with a substation on Farmer Road near Conyers. The state filing values it at about $1.2 billion. It is the one Rockdale data center approved for construction.
Where things stand: The only Rockdale data center approved for construction as of May 2026 (per WSB-TV).
π Latest update (Jan 17, 2024): DC Blox filed three data center buildings (about 1 million square feet) for state regional review (DRI #4120).
What we know
- π Where1726 Farmer Road NW, Conyers area, Unincorporated Rockdale County, Rockdale County
- π’ CompanyDC Blox
- π Where the power comes fromPlans include a substation.
- π§ WaterRockdale Water Resources Β· 785 gallons a day
- π΅ Cost$1.2 billion
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is it under construction? π I'll find out
- How many megawatts will it use? π I'll find out
What happened so far
- Jan 17, 2024DC Blox filed three data center buildings (about 1 million square feet) for state regional review (DRI #4120).
Local votes and rules
βΈοΈ Pause on new data centers
Rockdale County extended its pause on data centers and battery storage sites through September 8, 2026 (Resolution 2026-12, amending Resolution 2026-01), while it rewrites its development code. A rezoning for the Project Rockforge data center in Conyers was headed to a vote on October 6, 2026.
Drag the slider to compare the land before and now.
Where this comes from
- DRI #4120: DC Blox - ATL East Data Center (Development of Regional Impact filing) Β· Georgia Department of Community Affairs Β· Jan 17, 2024
- DRI #4120: DC Blox - ATL East Data Center, Additional Information Form Β· Georgia Department of Community Affairs Β· Jan 17, 2024
- Neighbors spend hours telling leaders why Rockdale County doesn't need another data center Β· WSB-TV Β· May 13, 2026