Approved, not built yet

DC BLOX Atlanta East data center (Farmer Road)

Also called: DC Blox ATL East

DC BLOX plans three data center buildings, about 1 million square feet, with a substation on Farmer Road near Conyers. The state filing values it at about $1.2 billion. It is the one Rockdale data center approved for construction.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: The only Rockdale data center approved for construction as of May 2026 (per WSB-TV).

πŸ•’ Latest update (Jan 17, 2024): DC Blox filed three data center buildings (about 1 million square feet) for state regional review (DRI #4120).

What we know

  • πŸ“ Where1726 Farmer Road NW, Conyers area, Unincorporated Rockdale County, Rockdale County
  • 🏒 CompanyDC Blox
  • πŸ”Œ Where the power comes fromPlans include a substation.
  • πŸ’§ WaterRockdale Water Resources Β· 785 gallons a day
  • πŸ’΅ Cost$1.2 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Jan 17, 2024
    DC Blox filed three data center buildings (about 1 million square feet) for state regional review (DRI #4120).

Local votes and rules

⏸️ Pause on new data centers

Rockdale County extended its pause on data centers and battery storage sites through September 8, 2026 (Resolution 2026-12, amending Resolution 2026-01), while it rewrites its development code. A rezoning for the Project Rockforge data center in Conyers was headed to a vote on October 6, 2026.

May 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. DRI #4120: DC Blox - ATL East Data Center (Development of Regional Impact filing) Β· Georgia Department of Community Affairs Β· Jan 17, 2024
  2. DRI #4120: DC Blox - ATL East Data Center, Additional Information Form Β· Georgia Department of Community Affairs Β· Jan 17, 2024
  3. Neighbors spend hours telling leaders why Rockdale County doesn't need another data center Β· WSB-TV Β· May 13, 2026

See something wrong? Tell us and we'll fix it.