DC BLOX Atlanta East data center (Farmer Road)
Also called: DC Blox ATL East
DC BLOX plans three data center buildings, about 1 million square feet, with a substation on Farmer Road near Conyers. The state filing values it at about $1.2 billion. It is the one Rockdale data center approved for construction.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Rockdale County Board of Commissioners (for land outside city and town limits).
Where things stand: Approved, not built yet The only Rockdale data center approved for construction as of May 2026 (per WSB-TV).
❓ 1 open question about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (Jan 17, 2024): DC Blox filed three data center buildings (about 1 million square feet) for state regional review (DRI #4120).
What we know
- 📍 Where1726 Farmer Road NW, Conyers area, Unincorporated Rockdale County, Rockdale County
- 🏢 CompanyDC Blox
- ⚡ Power it needs154 megawatts (about as much as 123,200 homes)
- 🔌 Where the power comes fromPlans include a substation.
- 💧 WaterRockdale Water Resources · 785 gallons a day
- 💵 Cost$1.2 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is it under construction? 🙋 I'll find out ·
What happened so far
- Jan 17, 2024DC Blox filed three data center buildings (about 1 million square feet) for state regional review (DRI #4120).
Local votes and rules
📜 Data center rules
Rockdale County commissioners approved the data center section (Section 9.5.3) of the county's new development code on Oct. 6, 2026. Before the vote they removed two parts that could have let projects already in the works claim the older rules. The county's pause on new data center and battery storage applications was extended only through Oct. 9, 2026.
✋ Turned down
Rockdale County commissioners denied all four requests for Project Rock Forge, a data center campus on about 300 acres of mostly residential land at Farmer Road and Irwin Bridge Road. One commissioner stepped aside from the votes.
⏸️ Pause on new data centers
Rockdale County extended its pause on data centers and battery storage sites through September 8, 2026 (Resolution 2026-12, amending Resolution 2026-01), while it rewrites its development code. A rezoning for the Project Rockforge data center in Conyers was headed to a vote on October 6, 2026.
Drag the slider to compare the land before and now.
Where this comes from
- DRI #4120: DC Blox - ATL East Data Center (Development of Regional Impact filing) · Georgia Department of Community Affairs · Jan 17, 2024
- DRI #4120: DC Blox - ATL East Data Center, Additional Information Form · Georgia Department of Community Affairs · Jan 17, 2024
- Neighbors spend hours telling leaders why Rockdale County doesn't need another data center · WSB-TV · May 13, 2026
- DRI #4120 Initial Information Form: DC Blox - ATL East Data Center (location field) · Georgia Department of Community Affairs · Oct 7, 2026
- U.S. Census geocoder: 1726 Farmer Road NW, Conyers, GA · U.S. Census Bureau · Oct 7, 2026
- Atlanta East Hyperscale Data Center Campus - Rockdale County, GA · DC BLOX · Oct 10, 2026
See something wrong? Tell us and we'll fix it.