No project in Turin Town, but 10 nearby
Who decides here: the Town Council of Turin Town votes on zoning. The Coweta County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Project Oak data center
Unincorporated Coweta County, Coweta County
255 acres
🕒 Aug 25, 2026: Commissioners unanimously denied the request to allow a data center. The county got 121 …
Proposedabout 8 miles awayBridgeport data center campus (Bridgeport Industrial Park)
Unincorporated Coweta County, Coweta County
🕒 Aug 3, 2026: The regional commission issued its finding on the project.
Proposedabout 10 miles awayCentral Coweta Industrial Phase II data centers
Unincorporated Coweta County, Coweta County
458 acres
🕒 Oct 27, 2025: The regional commission issued its finding on the project.
Being builtabout 11 miles awayQTS Fayetteville data center campus (Project Excalibur)
Fayetteville, Fayette County
615 acres
🕒 June 2026: Flint Riverkeeper and residents announced a Clean Water Act lawsuit over muddy stormwate…
Proposedabout 12 miles awayQTS ATL2 East data center
Fayetteville, Fayette County
313 acres
🕒 April 21, 2026: The regional commission issued its finding on the project.
Proposedabout 12 miles awayT5 ATL IV data center (Coweta County site)
Unincorporated Coweta County, Coweta County
200 acres
🕒 Oct 12, 2026: The county said a public hearing on rezoning the 200-acre Project Pegasus site is set fo…
What you can do
- Get told first.
We'll email you if anything changes in Turin Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Georgia Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.