Send us a tip
ProposedBig (AI-size): 1,500 megawatts

Bridgeport data center campus (Bridgeport Industrial Park)

Also called: Bridgeport (Revised)

An old industrial park approved in 2015 near I-85 is now proposed for data centers. The state filing lists about 8.25 million square feet, a power request of up to 1,500 megawatts and about 500,000 gallons of water a day. It values the project at $3 to $5 billion.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Coweta County Board of Commissioners (for land outside city and town limits).

Where things stand: Proposed Filed for state review in April 2026. The land is already zoned industrial.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Aug 3, 2026): The regional commission issued its finding on the project.

What we know

  • 📍 WhereBridgeport Parkway, on U.S. 27/29 near I-85 (the old industrial park also reaches into the Town of Moreland), Unincorporated Coweta County, Coweta County
  • 🏢 CompanyNot named (represented by McKagen Jones Law Firm)
  • ⚡ Power it needs1,500 megawatts (about as much as 1,200,000 homes)
  • 🔌 Where the power comes fromGeorgia Power. Power lines exist, but new substations would be needed. The filing asks for up to 1,500 megawatts.
  • 💧 WaterCoweta County Water and Sewerage Authority · 500,000 gallons a day
  • 👷 Jobs promised200

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is the developer and end user? 🙋 I'll find out ·
  • Does it need any new county vote, since the land is already zoned industrial? 🙋 I'll find out ·
  • Where will 1,500 megawatts of power come from? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • April 28, 2026
      Coweta County filed the revised Bridgeport project for state regional review (DRI #4727): about 8.25 million square feet.
    • Aug 3, 2026
      The regional commission issued its finding on the project.

    Local votes and rules

    📜 Data center rules

    Coweta County staff showed commissioners a rewrite of the data center rules at a work session in October 2026. Data centers would no longer be allowed in light industrial zones, and in industrial zones they would need a special permit from the board. A public hearing will come later.

    Oct 2026

    🗳️ Public vote

    A residents' group, Citizens for Rural Coweta, filed a petition with more than 14,800 voter signatures at the probate court. It asks for a countywide vote to change the county's data center zoning rules. The court must review the petition first.

    Oct 2026

    ✋ Turned down

    Coweta County commissioners unanimously denied a request to change the zoning conditions on an industrial site off Walt Sanders Road so it could become the Project Oak data center. The land stays limited to office or warehouse use of up to 2.1 million square feet.

    Aug 2026

    ⏸️ Pause on new data centers

    In June 2026 Coweta County commissioners paused data center applications, permits, rezonings and hearings for 180 days while they rewrite the county's data center rules. The pause ends Dec. 13, 2026, or sooner if new rules pass. Projects filed earlier (Project Sail, Project Peach, Bridgeport and Project Pegasus) are not covered.

    June 2026

    ⚖️ Court case

    Nineteen residents sued Coweta County and Atlas Development, asking the court to void the Project Sail rezoning and block the data center. They say the county broke its own rules and state rules and that the plans understated wetlands, power and water needs.

    May 5, 2026

    🗺️ Zoning change

    Coweta County commissioners voted 3-2 to approve a rezoning for Project Sail, a nine-building data center campus on about 830 acres near Newnan off Welcome to Sargent Road and Wagers Mill Road. It could use up to 900 megawatts. The chairman's motion to deny failed. A residents' group, Citizens for Rural Coweta, said it is weighing legal action.

    April 7, 2026

    📜 Data center rules

    Coweta County commissioners adopted data center rules 4-1 in December 2025, as the county's pause ended Dec. 17. Data centers are allowed only in industrial zones on sites of at least 25 acres, at least 300 feet from homes. Open-loop cooling is banned and generator tests are limited to weekday business hours.

    Dec 2025

    ⏸️ Pause on new data centers

    Coweta County passed a 180-day pause on data centers in May 2025 to study how other counties handle them and write an ordinance. It ended November 3, 2025. The draft ordinance allows data centers in light industrial and industrial zones with strict rules on buffers, noise, lighting, traffic and utilities.

    May 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4727: Bridgeport (Revised) (Development of Regional Impact filing) · Georgia Department of Community Affairs · April 28, 2026
    2. DRI #4727: Bridgeport (Revised), Additional Information Form · Georgia Department of Community Affairs · April 28, 2026
    3. Bridgeport project revived with proposed data centers · The Newnan Times-Herald · May 7, 2026
    4. DRI #4727 Initial Information Form: Bridgeport (Revised) (location field) · Georgia Department of Community Affairs · Oct 7, 2026
    5. OpenStreetMap: Bridgeport Parkway · OpenStreetMap contributors · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.