No project in Whitesburg City, but 6 nearby
Who decides here: the City Council of Whitesburg City votes on zoning. The Carroll County may review big projects too.
Nearby (within 15 miles)
Project Sail data center campus (Prologis / Atlas Development)
Unincorporated Coweta County, Coweta County
832 acres
π June 10, 2025: The regional commission issued its finding on the project.
Proposedabout 11 miles awayCentral Coweta Industrial Phase II data centers
Unincorporated Coweta County, Coweta County
458 acres
π Oct 27, 2025: The regional commission issued its finding on the project.
Stopped or cancelledabout 13 miles awayProject Oak data center
Unincorporated Coweta County, Coweta County
255 acres
π Aug 25, 2026: Commissioners unanimously denied the request to allow a data center. The county got 121 β¦
Proposedabout 13 miles awayBridgeport data center campus (Bridgeport Industrial Park)
Unincorporated Coweta County, Coweta County
π Aug 3, 2026: The regional commission issued its finding on the project.
Approved, not built yetabout 13 miles awayProject Peach data center campus (CyrusOne)
Unincorporated Coweta County, Coweta County
320 acres
π April 15, 2025: Coweta County commissioners approved the rezoning 3-2. Conditions include a 45-decibel nβ¦
Status unclearabout 15 miles awayT5 ATL IV data center (Coweta County site)
Unincorporated Coweta County, Coweta County
200 acres
π May 5, 2025: T5 filed a different 'T5 ATL IV' project in the City of Fairburn (DRI #4465).
What you can do
- Get told first.
We'll email you if anything changes in Whitesburg City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Whitesburg City: Georgia Power Co. (company) or Carroll Electric Member Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.