πŸ§ͺ Preview: Pennsylvania test version. Other states are being added.
πŸ“£ Report Something
Approved, not built yet

Project Sail data center campus (Prologis / Atlas Development)

Also called: Project Sail, Stop Project Sail Newnan Data Center

Project Sail is a 900-megawatt data center campus on about 832 acres near Newnan. Coweta County commissioners approved the rezoning after strong pushback from residents. The plan shrank to nine buildings (about 4.3 million square feet). The first state filing listed up to 9.1 million gallons of water a day.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Coweta County commissioners approved the rezoning. Prologis had not yet closed on buying the land, DCD reported.

πŸ•’ Latest update (June 10, 2025): The regional commission issued its finding on the project.

What we know

  • πŸ“ WhereNear Welcome Sargent Road and Wagers Mill Road, near Newnan, Unincorporated Coweta County, Coweta County
  • 🏒 CompanyAtlas Development, LLC (original applicant)
  • πŸ›οΈ Owned byPrologis (planned buyer)
  • 🌳 Size832 acres
  • ⚑ Power it needs900 megawatts (about as much as 720,000 homes)
  • πŸ’§ WaterCoweta County Water & Sewerage Authority Β· 9,100,000 gallons a day
  • πŸ’΅ Cost$17.2 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Dec 31, 2024
    Atlas Development filed Project Sail for state regional review (DRI #4361): 13 buildings, value about $17 billion.
  • June 10, 2025
    The regional commission issued its finding on the project.

Local votes and rules

βœ‹ Turned down

Coweta County commissioners unanimously denied a request to change the zoning conditions on an industrial site off Walt Sanders Road so it could become the Project Oak data center. The land stays limited to office or warehouse use of up to 2.1 million square feet.

Aug 2026

πŸ—ΊοΈ Zoning change

Coweta County commissioners voted 3-2 to approve a rezoning for Project Sail, a nine-building data center campus on about 830 acres near Newnan off Welcome to Sargent Road and Wagers Mill Road. It could use up to 900 megawatts. The chairman's motion to deny failed. A residents' group, Citizens for Rural Coweta, said it is weighing legal action.

April 7, 2026

⏸️ Pause on new data centers

Coweta County passed a 180-day pause on data centers in May 2025 to study how other counties handle them and write an ordinance. It ended November 3, 2025. The draft ordinance allows data centers in light industrial and industrial zones with strict rules on buffers, noise, lighting, traffic and utilities.

May 2025
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

RecentRecent
Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. DRI #4361: Project Sail (Development of Regional Impact filing) Β· Georgia Department of Community Affairs Β· Dec 31, 2024
  2. DRI #4361: Project Sail, Additional Information Form Β· Georgia Department of Community Affairs Β· Dec 31, 2024
  3. Prologis' 900MW 'Project Sail' gets the go-ahead in Coweta County, Georgia Β· Data Center Dynamics
  4. Fisher Explains Vote Against Project Oak Data Center Β· The Citizen (Fayette County) Β· Sept 1, 2026

See something wrong? Tell us and we'll fix it.