Send us a tip
ProposedBig (AI-size): 428 acres

Avemore technology and data park (Atlas Development)

Also called: Avemore

Atlas Development wants to turn about 428 acres in Villa Rica, once planned for about 500 homes, into a data center park. Earlier site plans showed seven 350,000-square-foot buildings and a $5-7 billion investment. The first phase could start in 2028.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Villa Rica City.

Where things stand: Proposed Filed for state review in April 2025 (refiled after a first filing was withdrawn). We found no final city vote.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (April 11, 2025): Atlas Development refiled the 428-acre Avemore technology park for state regional review (DRI #4451).

What we know

  • 📍 WhereCarroll County side of Villa Rica, along Hwy 61, Hickory Level and South Van Wert (includes Goldworth Road farm land), Villa Rica, Carroll County
  • 🏢 CompanyAtlas Development
  • 🌳 Size428 acres
  • 💧 WaterCarroll County

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 6, 2024
      First state regional review filing for Avemore (DRI #4347), later withdrawn.
    • April 11, 2025
      Atlas Development refiled the 428-acre Avemore technology park for state regional review (DRI #4451).
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4451: Avemore (Development of Regional Impact filing) · Georgia Department of Community Affairs · April 11, 2025
    2. DRI #4347: Avemore (first filing, withdrawn) (Development of Regional Impact filing) · Georgia Department of Community Affairs · Dec 6, 2024
    3. Atlas files for 428-acre technology and data park outside Atlanta, Georgia · Data Center Dynamics · 2025
    4. DRI #4347 Initial Information Form: Avemore (location field) · Georgia Department of Community Affairs · Oct 7, 2026
    5. Census TIGERweb roads: S Van Wert Rd x State Rte 61, Carroll County · U.S. Census Bureau · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.