1 data center project in Unincorporated Uinta County
Who decides here: the Uinta County Commissioners decides on zoning for land outside city and town limits.
In Unincorporated Uinta County
Local votes and rules
βοΈ Court case Β· Uinta County
Residents asked the district court to review and cancel the county's permits for the Prometheus data center. They said there were secret meetings and conflicts of interest, and that a water study was needed. The county denied this. A judge dismissed the case on Aug. 17, 2026, so the permits stand.
β Approved Β· Uinta County
County commissioners unanimously granted a conditional use permit for Prometheus Hyperscale's 1.25-gigawatt data center on about 506 acres east of Evanston. The permit has about 30 conditions, including dust and noise limits, closed-loop cooling, and protecting local electric rates.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Uinta County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Unincorporated Uinta County: Bridger Valley Electric Assn, Inc. (not available) or Pacificorp (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Wyoming.
π Open tasks here
- Which tech company will use the Evanston data center?
- What are the 30 permit conditions?
- How much gas will the on-site power plant burn, and what air permits are needed?