Roxbury Technology Park (Diode Ventures)
Charles City County, Charles City County
515 acres
🕒 Aug 18, 2025: Diode Ventures withdrew the project.
Proposedabout 13 miles awayIron Mountain data center campus (White Oak Technology Park)
Henrico County, Henrico County
66 acres
🕒 Feb 2025: Iron Mountain announced the Henrico campus.
Reported in the news, not confirmed yet
Approved, not built yetabout 14 miles awayQTS RIC4 and RIC5 expansions (White Oak / Varina)
Henrico County, Henrico County
1,100 acres
🕒 2026: QTS applied to the Virginia DEQ to permit 370 more diesel generators.
Reported in the news, not confirmed yet
Local votes and rules
📌 Other
Supervisors voted to stop work on a proposed 1,800-acre technology overlay district along the Route 33 corridor that would have opened land to data centers. They also passed a motion meant to hold off data center applications until the county adopts data center rules.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated New Kent County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Virginia Electric & Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.