Status unclearBig (AI-size): 180 acres

Iron Horse data center park (near Ashland)

Developers proposed an industrial campus for several data centers near Ashland, close to Dominion power lines, on land already zoned for homes and shops. They promised $16.5 million a year in taxes. Local planners disagreed about it in late 2024.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Hanover County Board of Supervisors (for land outside city and town limits).

Where things stand: Status unclear In December 2024 the Hanover and Ashland planning bodies split on it. A tracker lists it as canceled, but we found no official record of that.

❓ 1 open question about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Dec 2024): Hanover and Ashland planning commissions split on the proposal.

What we know

  • 📍 WhereHanover County, Hanover County
  • 🏢 CompanyTradeport Hanover Land / WestDulles Properties
  • 🌳 Size180 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Was the application formally withdrawn or denied, and when? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 2024
      Hanover and Ashland planning commissions split on the proposal.

    Local votes and rules

    ✅ Approved

    The county planning commission voted 5-2 to recommend rezoning about 78 acres at 10171 E. Patrick Henry Road for WestDulles Properties' Iron Horse data center campus, with buildings up to 75 feet. Some members noted no noise study had been done. Supervisors make the final decision.

    Aug 20, 2026

    📌 Other

    Supervisors voted unanimously to bring back the tax on data center computer equipment at 45 cents per $100 of value. They did not adopt a proposed raise of up to $3 per $100.

    June 2026

    ✋ Turned down

    Supervisors voted 4-3 to deny Tract's request to rezone about 430 acres on Mountain Road and Winns Church Road for the Mountain Road Technology Park, with five data center buildings and up to three substations near the Chickahominy River.

    May 27, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Hanover, Ashland split over data center park proposal · VPM · Dec 12, 2024
    2. One data center project pulled and another delayed in Hanover, as supervisors reinstitute equipment tax · Richmond BizSense · June 26, 2026