Stopped or cancelledBig (AI-size): 100 megawatts

Project Flash (Crusoe) at Summit View Business Park

Also called: Project Flash

The AI company Crusoe looked at a 50 to 100 megawatt data center on county land near Rocky Mount. After months of pushback from residents, the county said the project was dropped.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled The county said in August 2026 that the project will not go forward.

📣 See work going on anyway? Tell us

Last checked Oct 10, 2026.

🕒 Latest update (Aug 16, 2026): A county supervisor said Project Flash is not proceeding.

What we know

  • 📍 WhereSummit View Business Park near Rocky Mount, Franklin County, Franklin County
  • 🏢 CompanyCrusoe
  • 🌳 Size150 acres
  • ⚡ Power it needs100 megawatts (about as much as 80,000 homes)

What happened so far

  • July 2026
    Residents learned about the plan, called Project Flash.
  • Aug 16, 2026
    A county supervisor said Project Flash is not proceeding.

Local votes and rules

📌 Other

Three residents filed a complaint saying county leaders broke Virginia's open government and conflict-of-interest laws in secret talks over 'Project Flash', including agreements to keep plans private (NDAs). The case was moved to the Lynchburg prosecutor, who was reviewing it. In August 2026 a supervisor said Project Flash would not go forward.

July 1, 2026
🛰️ See it from above

Drag the slider to compare the land before and now.

20182025
We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Data center proposal dropped in Franklin County · WDBJ · Aug 16, 2026
  2. Franklin County data center project is no longer moving forward · WSET ABC13 · Aug 2026