Cipher Black Pearl AI data center for Amazon (near Wink)

Also called: Black Pearl, Cipher Black Pearl LLC

Cipher turned its bitcoin mining site near Wink into an AI data center for Amazon. The first part opened in August 2026, and the rest is being built.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: First part opened for Amazon in August 2026. More data halls are still being built.

๐Ÿ•’ Latest update (Aug 2026): First data center space was handed over to Amazon and rent began.

What we know

  • ๐Ÿ“ WhereAbout 75 acres near Wink, Unincorporated Winkler County, Winkler County
  • ๐Ÿข CompanyCipher Digital (formerly Cipher Mining)
  • ๐Ÿ›๏ธ Owned byCipher Digital Inc.
  • ๐Ÿ‘ค Built forAmazon Web Services (15-year lease)
  • ๐ŸŒณ Size75 acres
  • โšก Power it needs300 megawatts (about as much as 240,000 homes)
  • ๐Ÿ”Œ Where the power comes fromTexas power grid (ERCOT); approved for 300 megawatts

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Dec 2023
    Cipher took over a land lease of about 75 acres in Winkler County to build a data center.
  • Oct 2025
    Cipher signed a 15-year lease with Amazon Web Services for about 300 megawatts of AI data center space at the site, which had been a bitcoin mine.
  • Aug 2026
    First data center space was handed over to Amazon and rent began.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Cipher Digital Form 10-K for 2025 ยท Cipher Digital / SEC EDGAR ยท Feb 24, 2026
  2. Cipher Digital Q2 2026 business update ยท Cipher Digital / SEC EDGAR ยท Aug 4, 2026

See something wrong? Tell us and we'll fix it.