Calvano hyperscale data center (Northwest Freeway and City View Drive, Wichita Falls)
Also called: Calvano Wichita Falls
A California developer plans a $5 billion data center and battery site on about 227 acres near Northwest Freeway and City View Drive in north Wichita Falls. The City Council rezoned the land from residential to light industrial in November 2024. The developer said in 2026 that it had not yet filed state paperwork or asked for city water.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Wichita Falls City.
Where things stand: Proposed Land was rezoned in Nov. 2024; developer says the project is still in pre-development.
❓ 2 open questions about it: see below.
Last checked Oct 6, 2026.
🕒 Latest update (Nov 5, 2024): Wichita Falls City Council rezoned about 227 acres from residential to light industrial for the data center.
What we know
- 📍 WhereNear Northwest Freeway and City View Drive, Wichita Falls, Wichita County
- 🏢 CompanyCalvano Development
- 🌳 Size227 acres
- 💧 WaterCity of Wichita Falls (not yet requested)
- 💵 Cost$5 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will the city sell water to the data center, and how much? 🙋 I'll find out ·
- When will building start? 🙋 I'll find out ·
What happened so far
- Nov 5, 2024Wichita Falls City Council rezoned about 227 acres from residential to light industrial for the data center.
Drag the slider to compare the land before and now.
Where this comes from
- One data center planned for Wichita Falls is 'not there yet' · Times Record News (via Yahoo News) · 2026
- Texas data centers map and list · Cleanview (tracker) · Oct 2026
See something wrong? Tell us and we'll fix it.