Vulcan Core wanted a permit for a bitcoin mining data center near downtown Tyler. Neighbors worried about noise and water. The city planning board denied the permit in July 2026.
Where things stand: Planning and Zoning Commission voted 5-2 to deny the special use permit on July 7, 2026.
๐ Latest update (July 7, 2026): Tyler Planning and Zoning Commission voted 5-2 to deny the permit, as city staff advised.
What we know
- ๐ WhereW. Erwin Street, near downtown (light industrial land), Tyler, Smith County
- ๐ข CompanyVulcan Core
- ๐ค Built forBarrio (data center operator, planned tenant)
- ๐ Where the power comes fromOncor power already at the site.
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did the developer appeal to the City Council? ๐ I'll find out
What happened so far
- June 15, 2026Developer held a community meeting.
- July 7, 2026Tyler Planning and Zoning Commission voted 5-2 to deny the permit, as city staff advised.
Local votes and rules
โ Turned down
Tyler's Planning and Zoning Commission voted 5-2 to deny a special use permit for a bitcoin mining data center by Vulcan Core on W. Erwin Street near downtown. City planning staff also recommended denial over water use, noise and the lack of a zoning category for data centers. The developer can appeal to City Council.
Drag the slider to compare the land before and now.
Where this comes from
- Tyler planning commission denies permit for proposed data center ยท KLTV ยท July 7, 2026