Energy Vault AI campus with Crusoe modular data centers (Snyder)
Also called: Crusoe Spark
Battery company Energy Vault is building a small AI data center campus in Snyder using 10 box-like modular units from Crusoe. It starts at 8 megawatts in 2027 and could grow much bigger later.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Scurry County Commissioners Court (for land outside city and town limits).
Where things stand: Being built Site work began in July 2026. First 8 megawatts expected to run in early 2027.
❓ 3 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (July 27, 2026): Energy Vault began building an AI campus in Snyder with 10 Crusoe Spark modular data centers, starting at 8 megawatts and growing to 25, with long-term plans up to 500 megawatts.
What we know
- 📍 WhereSnyder area (city-limits status not stated in sources we opened), Unincorporated Scurry County, Scurry County
- 🏢 CompanyEnergy Vault
- 👤 Built forCrusoe Cloud customers
- ⚡ Power it needs25 megawatts (about as much as 20,000 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is the site inside Snyder city limits? 🙋 I'll find out ·
- Where will its power come from? 🙋 I'll find out ·
- Will it grow toward 500 megawatts? 🙋 I'll find out ·
What happened so far
- July 27, 2026Energy Vault began building an AI campus in Snyder with 10 Crusoe Spark modular data centers, starting at 8 megawatts and growing to 25, with long-term plans up to 500 megawatts.
Drag the slider to compare the land before and now.
Where this comes from
- Energy Vault begins building AI infrastructure campus in Snyder · KCBD · July 28, 2026
- Energy Vault breaks ground on powered AI infrastructure campus in Texas · BIC Magazine · July 2026