EG AI small data center (Rice)
Also called: EG AI Rice Campus
EG AI Corp plans a small data center building, about 8,600 square feet and $5 million, in Rice in Navarro County, according to a state construction filing. It is much smaller than most data centers on this map.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Rice City.
Where things stand: Proposed Registered with the state on Oct. 5, 2026; construction planned Nov. 2026 to April 2028.
❓ 3 open questions about it: see below.
Last checked Oct 19, 2026.
🕒 Latest update (Oct 5, 2026): EG AI Corp registered a new 8,599 sq ft data center building at 800 NW McKinney St in Rice with the Texas Department of Licensing and Regulation (TABS2027002808), estimated at $5 million, with work planned Nov. 6, 2026 to April 30, 2028.
What we know
- 📍 Where800 NW McKinney St, Rice, Rice, Navarro County
- 🏢 CompanyEG AI Corp
- 💵 Cost$5 million
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts will it use? 🙋 I'll find out ·
- How will it be cooled, and will it use city water? 🙋 I'll find out ·
- Does it need any approval from the City of Rice? 🙋 I'll find out ·
What happened so far
- Oct 5, 2026EG AI Corp registered a new 8,599 sq ft data center building at 800 NW McKinney St in Rice with the Texas Department of Licensing and Regulation (TABS2027002808), estimated at $5 million, with work planned Nov. 6, 2026 to April 30, 2028.
Drag the slider to compare the land before and now.
Where this comes from
- TDLR TABS TABS2027002808: EG AI Rice Campus Data Center, 800 NW McKinney St, Rice · Texas Department of Licensing and Regulation · Oct 5, 2026
- Census geocoder: 800 NW McKinney St, Rice, TX · U.S. Census Bureau · Oct 19, 2026
See something wrong? Tell us and we'll fix it.