ProposedBig (AI-size): 2,000 megawatts

Microsoft Pecos AI data center with Chevron's Project Kilby gas plant

Also called: Project Kilby, Energy Forge One

Microsoft plans a 2-gigawatt AI data center near Pecos. Chevron would build a gas power plant next to it just for this site. Microsoft says it will take 5 to 7 years and create more than 6,000 construction jobs at peak.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Reeves County Commissioners Court (for land outside city and town limits).

Where things stand: Proposed Announced in June 2026. First power from the new gas plant is expected in 2028.

❓ 4 open questions about it: see below.

Last checked Oct 26, 2026.

🕒 Latest update (Sept 28, 2026): A state air permit (permit by rule) for the 'Kilby Power Plant: Project Kilby - Chevron and Microsoft' finished its first engineer review at TCEQ. It has not been issued.

What we know

  • 📍 WhereNear the city of Pecos (exact site not published in sources we opened), Unincorporated Reeves County, Reeves County
  • 🏢 CompanyMicrosoft (data center); Chevron with Engine No. 1 and GE Vernova (power plant)
  • 🏛️ Owned byMicrosoft
  • 👤 Built forMicrosoft
  • ⚡ Power it needs2,000 megawatts (about as much as 1,600,000 homes)
  • 🔌 Where the power comes fromChevron's new gas power plant next to the site (Project Kilby), growing to 2.67 gigawatts, under a 20-year deal. Not connected to the grid at first.
  • ❄️ CoolingClosed-loop cooling; Microsoft says only an initial fill of water is needed

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Exactly where is the site, and is it inside Pecos city limits? 🙋 I'll find out ·
  • Has Chevron made its final decision to build the power plant? 🙋 I'll find out ·
  • Did Reeves County or Pecos give tax breaks? 🙋 I'll find out ·
  • How many permanent jobs will there be? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • June 22, 2026
      Microsoft announced a 2-gigawatt data center in Pecos. Chevron signed a 20-year deal to power it with a new gas plant.
    • Sept 28, 2026
      A state air permit (permit by rule) for the 'Kilby Power Plant: Project Kilby - Chevron and Microsoft' finished its first engineer review at TCEQ. It has not been issued.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Powering the next wave of AI: expanding capacity with our new datacenter in Pecos · Microsoft · June 22, 2026
    2. Microsoft 2-gigawatt AI data center in West Texas with onsite gas · The Energy Mag · June 22, 2026
    3. Summary: Data Center Permits Issued by TCEQ After 9/21/2026 · Public Citizen (summary of TCEQ records) · Oct 19, 2026

    See something wrong? Tell us and we'll fix it.