Being builtBig (AI-size): 1,000 megawatts

Riot Platforms Corsicana campus (1 GW)

Riot built a large bitcoin mine near Corsicana with 1 gigawatt of approved power. On Nov. 4, 2026, Riot said it signed a 15-year lease of the whole 332-acre campus, 910 megawatts of computing space, with an AI company it did not name. The space is to be handed over in three parts, from September 2027 to July 2028.

👥 Reported, not confirmed yetSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Navarro County Commissioners Court (for land outside city and town limits).

Where things stand: Being built Bitcoin mine running since 2024. In Nov. 2026 Riot said it leased the whole campus (910 MW) to an AI company, with delivery planned from Sept. 2027 to July 2028.

❓ 4 open questions about it: see below.

Last checked Nov 9, 2026.

🕒 Latest update (Nov 4, 2026): Riot said it signed a 15-year lease of its whole Corsicana campus (910 MW of computing space on 332 acres) with an AI company it did not name. The space is to be delivered in three parts: 400 MW in Sept. 2027, 200 MW in Jan. 2028 and 310 MW in July 2028.

What we know

  • 📍 Where6980 FM 709 S, outside Corsicana, Unincorporated Navarro County, Navarro County
  • 🏢 CompanyRiot Platforms
  • 👤 Built forunnamed AI company (Riot calls it a 'leading Frontier AI Lab')
  • 🌳 Size332 acres
  • ⚡ Power it needs1,000 megawatts (about as much as 800,000 homes)
  • 🔌 Where the power comes fromDirect 345-kilovolt connection to the state grid (ERCOT), 1 gigawatt approved.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the site inside Corsicana city limits? 🙋 I'll find out ·
  • How much water will an AI data center here use? 🙋 I'll find out ·
  • Did Navarro County give tax breaks? 🙋 I'll find out ·
  • Which AI company leased the Corsicana campus? Riot has not named it. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: exact address found.

    What happened so far

    • 2023
      Construction began; site running by 2024.
    • Nov 4, 2026
      Riot said it signed a 15-year lease of its whole Corsicana campus (910 MW of computing space on 332 acres) with an AI company it did not name. The space is to be delivered in three parts: 400 MW in Sept. 2027, 200 MW in Jan. 2028 and 310 MW in July 2028.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Corsicana · Riot Platforms
    2. Welcome to Corsicana · Riot Platforms
    3. Census geocoder match for 6980 FM 709, Corsicana, TX 75110 · U.S. Census Bureau · Oct 7, 2026
    4. TDLR TABS TABS2026020144: Project Ditto (Riot Platforms), 6980 FM 709, Corsicana · Texas Department of Licensing and Regulation · Oct 7, 2026
    5. Riot Corsicana, TX · Baxtel · Oct 7, 2026
    6. Riot Platforms Reports Third Quarter 2026 Financial Results and Strategic Highlights · Riot Platforms · Nov 4, 2026

    See something wrong? Tell us and we'll fix it.