Send us a tip
Built & runningBig (AI-size): 700 megawatts

Riot Platforms Rockdale site (bitcoin mine turning into AI data center)

Riot runs one of the largest bitcoin mines in the US near Rockdale. It now rents space there to chip maker AMD for AI computing and plans to turn the whole 700-megawatt site into data centers.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

Where things stand: Built & running Runs as a bitcoin mine; first AI space for AMD delivered in 2026; Riot plans to convert all 700 MW.

❓ 4 open questions about it: see below.

📣 Report noise, water or power bill changes

Last checked Nov 9, 2026.

🕒 Latest update (May 1, 2026): AMD added 25 MW, for 50 MW in total.

What we know

  • 📍 Where2721 Charles Martin Hall Road, near Rockdale, Unincorporated Milam County, Milam County
  • 🏢 CompanyRiot Platforms
  • 👤 Built forAMD (first tenant, 50 MW)
  • 🌳 Size200 acres
  • ⚡ Power it needs700 megawatts (about as much as 560,000 homes)
  • 🔌 Where the power comes fromExisting 700-megawatt connection to the state grid (ERCOT).
  • 💸 Tax breaksMilam County approved a 10-year, 75% tax break (paid as a PILOT starting 2028) for a new data center; one commissioner voted no.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the site inside Rockdale city limits or in unincorporated Milam County? 🙋 I'll find out ·
  • How much water will the AI data center use? 🙋 I'll find out ·
  • Will noise change as it converts? 🙋 I'll find out ·
  • How many megawatts did the unnamed AI company lease at Rockdale, and when will it move in? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: exact address found.

    What happened so far

    • 2026
      Riot signed a data center lease at Rockdale with an AI company it did not name, the same company that later leased its Corsicana campus (as described in Riot's Nov. 4, 2026 report).
    • Jan 16, 2026
      Riot bought the 200-acre site for $96 million and signed a 10-year, 25 MW data center lease with AMD.
    • Feb 10, 2026
      Milam County commissioners approved a 10-year, 75% tax break for a new Riot data center.
    • May 1, 2026
      AMD added 25 MW, for 50 MW in total.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something