Being builtBig (AI-size): 375 acres
Google Midlothian data center campus (Railport Parkway) - building 5
Also called: Sharka Data Center
Google keeps adding to its large data center campus in Midlothian. A fifth building costing about $880 million is under construction and due in early 2027.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Midlothian City.
Where things stand: Being built Fifth building started late Jan. 2026; due Feb. 24, 2027.
❓ 3 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (Jan 2026): Construction of an $880 million fifth building (288,000 sq ft) began.
What we know
- 📍 Where3441 Railport Parkway, Midlothian, Ellis County
- 🏢 CompanySharka LLC (Google)
- 🏛️ Owned byAlphabet
- 👤 Built forGoogle
- 🌳 Size375 acres
- 💵 Cost$880 million
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power and water does the full campus use? 🙋 I'll find out ·
- Are more buildings planned? 🙋 I'll find out ·
- Will Google use the extra 165 acres it bought in Ellis County for more data centers? 🙋 I'll find out ·
🔎 What we checked
- Oct 7, 2026: We checked the site location: exact address found.
What happened so far
- March 2024Google filed a $100 million fourth building.
- Jan 2026Construction of an $880 million fifth building (288,000 sq ft) began.
🛰️ See it from above
Drag the slider to compare the land before and now.
20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- Google files for fifth data center at Midlothian campus in Texas · DatacenterDynamics · 2026
- Census geocoder match for 3441 Railport Pkwy, Midlothian, TX · U.S. Census Bureau · Oct 7, 2026
- Google to expand data center campus south of Dallas · Bisnow · Dec 10, 2025
See something wrong? Tell us and we'll fix it.