Cipher lists a site called Mikeska with up to 500 megawatts and expected power in 2028. A tracker places it in McCulloch County. Few other details are public.
Where things stand: Cipher used its option to buy the site in Feb. 2026; power expected in 2028.
๐ Latest update (Feb 2026): Cipher exercised its option on the Mikeska site.
What we know
- ๐ WhereUnincorporated McCulloch County, McCulloch County
- ๐ข CompanyCipher Mining (Cipher Digital)
- โก Power it needs500 megawatts (about as much as 400,000 homes)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Exactly where is the site? ๐ I'll find out
- Will it be for bitcoin mining or AI? ๐ I'll find out
- Where will the power and water come from? ๐ I'll find out
What happened so far
- Feb 2026Cipher exercised its option on the Mikeska site.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
Photos: USGS The National Map.
Where this comes from
- Cipher Mining annual report (Form 10-K) for 2025 ยท U.S. SEC (Cipher filing) ยท Feb 2026
- Texas data centers map and list ยท Cleanview (tracker) ยท Oct 2026