ProposedBig (AI-size): 132 acres
1606 Corp. AI data center at a Lufkin power plant
A small company called 1606 Corp. wants to buy a 55-megawatt power plant and a 50,000 sq ft building on 132 acres in Lufkin and use the power for AI computers. The deal is not final.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Lufkin City.
Where things stand: Proposed Non-binding deal to buy the plant; not final.
❓ 3 open questions about it: see below.
Last checked Oct 6, 2026.
🕒 Latest update (2026): 1606 Corp. signed a non-binding term sheet to buy the plant and 132 acres for about $11.67 million.
What we know
- 📍 WhereLufkin (a tracker lists it as the former Aspen Power plant), Lufkin, Angelina County
- 🏢 Company1606 Corp.
- 🌳 Size132 acres
- ⚡ Power it needs55 megawatts (about as much as 44,000 homes)
- 🔌 Where the power comes fromExisting 55 MW power plant on site, to power the computers directly (behind the meter).
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has the purchase closed? 🙋 I'll find out ·
- Will the plant restart, and what fuel will it burn? 🙋 I'll find out ·
- Is the site inside Lufkin city limits? 🙋 I'll find out ·
What happened so far
- 20261606 Corp. signed a non-binding term sheet to buy the plant and 132 acres for about $11.67 million.
🛰️ See it from above
Drag the slider to compare the land before and now.
20182025
We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- 1606 Corp. Enters into Term Sheet to Acquire Texas 55 MW Power Generation Facility · ACCESS Newswire (company release)
- 1606 Corp Lufkin AI Data Center (Former Aspen Power Plant) · More Than Just Parks data center tracker
See something wrong? Tell us and we'll fix it.