Texas Solar Works hyperscale data center plan (Northeast Lubbock)
Also called: Northeast Lubbock data center, 936-acre data center
A developer wanted to rezone 936 acres in northeast Lubbock for a giant data center with gas turbines and solar. Neighbors who already live near industry objected, and the planning board said no. The developer pulled the plan but said it might return.
What happens next?
Where things stand: Stopped or cancelled The city planning board voted 4-3 against the rezoning in January 2026. The developer withdrew and said it may come back with a new plan.
❓ 2 open questions about it: see below.
📣 See work going on anyway? Tell us
Last checked Oct 6, 2026.
🕒 Latest update (Jan 16, 2026): The developer withdrew its request before the City Council vote and said it would revise and resubmit.
What we know
- 📍 Where936 acres off Northeast Loop 289, southeast of East Municipal Drive, plus about 500 acres next to it outside the city for power equipment, Lubbock, Lubbock County
- 🏢 CompanyTexas Solar Works LLC (represented by Hugo Reed and Associates)
- 🌳 Size936 acres
- 🔌 Where the power comes fromGrid connection (ERCOT), a solar farm, and gas turbines on nearby county land
- 🗼 New power linesYes
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has Texas Solar Works filed a new plan with the city? 🙋 I'll find out ·
- Who was the planned end user? 🙋 I'll find out ·
What happened so far
- Jan 8, 2026Lubbock Planning and Zoning Commission voted 4-3 against rezoning 936 acres from homes to heavy industry for a hyperscale data center.
- Jan 16, 2026The developer withdrew its request before the City Council vote and said it would revise and resubmit.
Local votes and rules
⏸️ Pause on new data centers
Lubbock City Council voted to start the legal steps for a 90-day pause on requests and approvals for large data centers, which could be extended by 90 more days. Two council members voted no. Two public hearings come first (the first expected in November), and final passage needs three-quarters of the council. Residents had asked for an 18-month pause by petition.
📌 Other
Lubbock City Council unanimously passed a non-binding resolution saying large data centers will not be developed inside city limits until the council adopts rules to protect water, power, public health and safety.
Drag the slider to compare the land before and now.
Where this comes from
- Developer withdraws plan for northeast Lubbock data center · KCBD · Jan 16, 2026
- What Lubbock's city manager is asking from developers with AI data center proposals · HPPR / KTTZ · May 4, 2026
See something wrong? Tell us and we'll fix it.