Corva Project Infrared data center (Northeast Lubbock)
Also called: Project Infrared
A company called Corva plans a small data center in northeast Lubbock next to a city power substation. It would use up to 27 megawatts and about 1,500 gallons of water a day. The deal was approved before it was made public, which upset some residents.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Lubbock City.
Where things stand: Approved, not built yet Lubbock's economic development group (LEDA) approved a deal in June 2026. It still needs a power hookup from Lubbock Power & Light.
❓ 2 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (July 29, 2026): LEDA defended the deal after residents learned of it. It said the project is below the city's proposed 100-megawatt 'large-scale' limit.
What we know
- 📍 WhereNear Municipal Drive and Guava in northeast Lubbock, next to LP&L's Northeast Substation outside Loop 289. Land is already zoned light industrial., Lubbock, Lubbock County
- 🏢 CompanyCorva
- ⚡ Power it needs27 megawatts (about as much as 21,600 homes)
- 🔌 Where the power comes fromLubbock Power & Light grid (ERCOT); no power plant on site
- 💧 WaterCity of Lubbock · 1,500 gallons a day
- ❄️ CoolingClosed-loop cooling
- 💸 Tax breaksLEDA says no city incentives were given.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has Lubbock Power & Light approved the power hookup? 🙋 I'll find out ·
- Will the city's new data center rules apply to this project? 🙋 I'll find out ·
🔎 What we checked
- Oct 7, 2026: We checked the site location: approximate location found.
What happened so far
- June 2026LEDA's board approved a deal with Corva for a 50,000-square-foot data center. It starts at 6 megawatts and can grow to 27.
- July 29, 2026LEDA defended the deal after residents learned of it. It said the project is below the city's proposed 100-megawatt 'large-scale' limit.
Local votes and rules
⏸️ Pause on new data centers
Lubbock City Council voted to start the legal steps for a 90-day pause on requests and approvals for large data centers, which could be extended by 90 more days. Two council members voted no. Two public hearings come first (the first expected in November), and final passage needs three-quarters of the council. Residents had asked for an 18-month pause by petition.
📌 Other
Lubbock City Council unanimously passed a non-binding resolution saying large data centers will not be developed inside city limits until the council adopts rules to protect water, power, public health and safety.
Drag the slider to compare the land before and now.
Where this comes from
- LEDA defends data center deal with Corva in northeast Lubbock · KCBD · July 30, 2026
- Small plots of land fuel big suspicions among Lubbock residents who fear it's for a data center · Texas Tribune via KPRC · July 29, 2026
- OpenStreetMap search: East Municipal Drive at North Guava Avenue · OpenStreetMap contributors · Oct 7, 2026
See something wrong? Tell us and we'll fix it.