ProposedBig (AI-size): 200 megawatts
Prometheus Hyperscale campus (between Talty and Post Oak Bend City)
Prometheus Hyperscale plans a 200-megawatt, four-building data center campus on 500 acres in Kaufman County. It would make its own power with gas engines and use a nearby battery site.
What happens next?
🗓️ No meeting or deadline known yet.
Where things stand: Proposed Company announced the site; no local approvals reported yet.
❓ 3 open questions about it: see below.
Last checked Oct 6, 2026.
What we know
- 📍 WhereBetween Talty and Post Oak Bend City, unknown, Kaufman County
- 🏢 CompanyPrometheus Hyperscale (with Engie North America and Conduit Power)
- 🌳 Size500 acres
- ⚡ Power it needs200 megawatts (about as much as 160,000 homes)
- 🔌 Where the power comes fromOwn natural gas engines on site plus Engie's battery storage next door.
- ❄️ CoolingLiquid cooling
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is the site inside a city or in unincorporated Kaufman County? 🙋 I'll find out ·
- Has an air permit for the gas engines been filed? 🙋 I'll find out ·
- How much water will it use? 🙋 I'll find out ·
🛰️ See it from above
Drag the slider to compare the land before and now.
20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- Prometheus Hyperscale details plans for Dallas data center campus · DatacenterDynamics
See something wrong? Tell us and we'll fix it.