ProposedBig (AI-size): Described as an AI or hyperscale project in the sources

Raeden AI data center (old glass bottle plant, Jacinto City)

A company called Raeden wants to turn an old glass bottle plant in Jacinto City into an AI data center using up to 79 megawatts. The mayor and council oppose it but say they may not be able to stop it. The city is measuring noise now to set limits.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Jacinto City City.

Where things stand: Proposed City leaders oppose it; company wants to start work as early as Oct. 2026. May need a special use permit.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Sept 11, 2026): City held a town hall with residents and the company.

What we know

  • 📍 Where4202 Fidelity Street (former glass bottling plant), near homes and an elementary school, Jacinto City, Harris County
  • 🏢 CompanyRaeden
  • 🌳 Size30 acres
  • ⚡ Power it needs79 megawatts (about as much as 63,200 homes)
  • 🔌 Where the power comes fromOn-site substation fed by two 138-kilovolt power lines; marketing says 40 MW in 2026, up to 79 MW in two years.
  • 💧 WaterCompany says it would not need daily water use.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: exact address found.

    What happened so far

    • May 2026
      Sale brochure pitched the 30-acre site as a 'Houston Hyperscale' data center.
    • Sept 11, 2026
      City held a town hall with residents and the company.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Jacinto City neighbors fear 79-megawatt data beast moving in · Hoodline · May 2026
    2. Jacinto City leaders oppose proposed AI data center as company eyes October redevelopment · KPRC Click2Houston · Sept 11, 2026
    3. Census geocoder match for 4202 Fidelity St, Jacinto City, TX · U.S. Census Bureau · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.