Core Scientific / Telios AI data center campus (Wieland, Hunt County)
Core Scientific plans a large AI data center campus on about 265 acres of farmland in the Wieland area of Hunt County. It would use about 430 megawatts and start getting power in 2027.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Hunt County Commissioners Court (for land outside city and town limits).
Where things stand: Proposed Presented to Hunt County commissioners Mar. 24, 2026; power to start in 2027, full power by 2029.
❓ 4 open questions about it: see below.
Last checked Nov 16, 2026.
🕒 Latest update (Nov 2026): Telios Quinlan One, LLC registered state building plans (TDLR) for a 341,326-square-foot data center building at 4852 County Road 3507 near Quinlan, estimated at $1.3 billion, with work listed to start Nov. 24, 2026 and finish Sept. 2028.
What we know
- 📍 Where4642 County Road 3508, Wieland area near Quinlan, Unincorporated Hunt County, Hunt County
- 🏢 CompanyCore Scientific with Telios
- 🌳 Size265 acres
- ⚡ Power it needs430 megawatts (about as much as 344,000 homes)
- 🔌 Where the power comes fromNext to existing high-voltage lines, a solar farm and a battery site; about 430 MW of grid power planned.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will it use? 🙋 I'll find out ·
- Will Hunt County give a tax break? 🙋 I'll find out ·
- Who is the tenant? 🙋 I'll find out ·
- Has construction started on the first Core Scientific / Telios data center building in Hunt County? 🙋 I'll find out ·
🔎 What we checked
- Oct 7, 2026: We checked the site location: exact address found.
What happened so far
- March 10, 2026Core Scientific's plan for a 265-acre AI campus in Hunt County was first reported.
- March 24, 2026Core Scientific and Telios spoke to the Hunt County Commissioners Court.
- Nov 2026Telios Quinlan One, LLC registered state building plans (TDLR) for a 341,326-square-foot data center building at 4852 County Road 3507 near Quinlan, estimated at $1.3 billion, with work listed to start Nov. 24, 2026 and finish Sept. 2028.
Local votes and rules
📌 Other
Hunt County commissioners passed a resolution backing a proposed state bill. It would make developers of data centers and other big projects file a sworn public statement with the county at least 30 days before locking in power, water or construction. The statement would list the real owner, power and water needs, cooling type, on-site power and plans for shutting down.
Drag the slider to compare the land before and now.
Where this comes from
- How Hunt County's first AI data center came to be · eExtra News · March 25, 2026
- Census geocoder match for 4642 County Road 3508, Quinlan, TX 75474 · U.S. Census Bureau · Oct 7, 2026
- Core Scientific: Dallas (Hunt County site) · Baxtel · Oct 7, 2026
- TDLR TABS project TABS2027005763: Core Scientific - Hunt · Texas Department of Licensing and Regulation · Nov 2026
See something wrong? Tell us and we'll fix it.