Proposed
Provident data center on Hillsboro EDC land
Provident wants to buy 300 acres from Hillsboro's economic development group for a data center campus. Many residents oppose it. The group gave Provident more time to study the site before deciding.
Where things stand: City economic development group extended a pre-sale contract by four months in spring 2026 to study the sale.
๐ Latest update (April 24, 2026): Many residents spoke against the plan at a public meeting.
What we know
- ๐ WhereNorth Hillsboro, next to the city industrial park (land already zoned heavy industrial), Hillsboro, Hill County
- ๐ข CompanyProvident Realty Advisors (Provident Data Centers)
- ๐ณ Size300 acres
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did the Hillsboro EDC approve the land sale? ๐ I'll find out
- How much power and water would it use? ๐ I'll find out
What happened so far
- April 24, 2026Many residents spoke against the plan at a public meeting.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Concern over proposed sale of 300 acres for data center in Hillsboro, Texas ยท DatacenterDynamics ยท 2026
- Texas county pauses data center construction in rural areas for a year ยท San Antonio Current (Texas Tribune) ยท May 13, 2026
See something wrong? Tell us and we'll fix it.