Project Aquila (RCM Hill, unincorporated Hill County)
A developer called RCM Hill plans a 1,235-megawatt data center on more than 800 acres in rural Hill County. The county paused new data centers in May 2026, the developer sued, and the county lifted the pause in June. Big projects now must share facts on water, traffic, noise and economic effects and give public notice.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Hill County Commissioners Court (for land outside city and town limits).
Where things stand: Proposed County lifted its one-year pause on June 4, 2026 after the developer sued. The federal lawsuit was still open in June 2026.
❓ 4 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (June 4, 2026): Hill County commissioners voted unanimously to end the data center pause. They replaced it with a checklist: big projects must report water use, traffic, noise and economic effects and give public notice.
What we know
- 📍 WhereUnincorporated Hill County, Hill County
- 🏢 CompanyRCM Hill, LLC
- 🌳 Size800 acres
- ⚡ Power it needs1,235 megawatts (about as much as 988,000 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where exactly is the site? 🙋 I'll find out ·
- What will the federal court decide? 🙋 I'll find out ·
- Who is the end user? 🙋 I'll find out ·
- How much water and power will it use? 🙋 I'll find out ·
What happened so far
- May 12, 2026Hill County commissioners voted 3-2 for a one-year pause on new data centers outside city limits.
- May 28, 2026RCM Hill sued Hill County in federal court in Waco, calling the pause illegal.
- June 4, 2026Hill County commissioners voted unanimously to end the data center pause. They replaced it with a checklist: big projects must report water use, traffic, noise and economic effects and give public notice.
Local votes and rules
⚖️ Court case
Data center developer RCM Hill LLC sued Hill County and three county officials in federal court, asking for $100 million and saying the county's data center pause broke state law. The company is planning 'Project Aquila,' a 1,235-megawatt data center on more than 800 acres. After the county canceled the pause, the company dropped the case on July 9, 2026.
⏸️ Pause on new data centers
Hill County commissioners voted 3-2 for a pause of up to one year on new data centers, large batteries and power plants in unincorporated areas. After a data center developer sued, commissioners voted unanimously on June 4, 2026 to cancel the pause.
Drag the slider to compare the land before and now.
Where this comes from
- Data center developer files lawsuit over 'illegal' moratorium in Hill County, Texas · KWTX · May 28, 2026
- Hill County Commissioners Court rescinds moratorium on data center in the wake of lawsuit · KWTX · June 4, 2026
- Texas county lifts data center moratorium amid pressure from developer lawsuit · FOX 4 Dallas-Fort Worth · June 9, 2026
See something wrong? Tell us and we'll fix it.