Google data center campuses (Haskell County)
Also called: Google Thelma campus, Google North Haskell, Google South Haskell
Google is building two data centers in Haskell County, north of Abilene, as part of a $40 billion plan for Texas. One of them will be paired with a new solar and battery plant to lower its strain on the power grid. Trackers list a south campus near the Jones County line and a north campus.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Haskell County Commissioners Court (for land outside city and town limits).
Where things stand: Being built Google announced two Haskell County data centers in Nov. 2025; one is under construction.
❓ 5 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (Nov 14, 2025): Google announced $40 billion for Texas, including two data centers in Haskell County.
What we know
- 📍 Where10357 Loop Road (south campus); a second campus is planned in north Haskell County, Unincorporated Haskell County, Haskell County
- 🏢 CompanyGoogle
- 👤 Built forGoogle
- 🔌 Where the power comes fromOne of the two sites will be paired with a new solar and battery storage plant.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is the south ('Thelma') campus in Haskell County, or in Lueders / Jones County as one state filing says? 🙋 I'll find out ·
- Exactly where are the two sites, and are any inside a town? 🙋 I'll find out ·
- How much water will they use? 🙋 I'll find out ·
- Did Haskell County give Google a tax break? 🙋 I'll find out ·
- How many megawatts will each campus use? 🙋 I'll find out ·
🔎 What we checked
- Oct 7, 2026: We checked the site location: approximate location found.
What happened so far
- June 18, 2025Construction began on 'Data Center THM1A' (280,000 sq ft) at the 'THM campus' on Bean Road, listed under Lueders, Jones County, per a state filing.
- Nov 14, 2025Google announced $40 billion for Texas, including two data centers in Haskell County.
Drag the slider to compare the land before and now.
Where this comes from
- Google to build three new data centers in Texas in $40 billion investment · KSAT (Texas Tribune) · Nov 15, 2025
- Google files for two data centers in Vernon, Texas · DatacenterDynamics · 2026
- Data center to be built in Lueders, Texas · DatacenterDynamics · June 21, 2025
- Texas data centers map and list · Cleanview (tracker) · Oct 2026
- Texas StratMap address point: 10357 LOOP ROAD (Haskell County) · Texas Geographic Information Office (TxGIO) · Oct 7, 2026
- TDLR TABS TABS2025019833: Data Center THM1A (Homebound Group LLC), 10357 Loop Road, Haskell · Texas Department of Licensing and Regulation · Oct 7, 2026
See something wrong? Tell us and we'll fix it.