Approved, not built yet

Crusoe data center project (Haskell County)

Also called: Haskell County Crusoe RZ 2026, Haskell DC Owner LLC

Haskell County signed a tax break deal with Haskell DC Owner LLC, a company working through Crusoe, for one or more data centers on about 2,042 acres. The first phase is expected to cost about $1 billion. Instead of full taxes for 10 years, the company would pay at least $10 million a year.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: County approved a tax break deal in June 2026; no building start reported yet.

๐Ÿ•’ Latest update (June 23, 2026): County and Haskell DC Owner LLC signed the tax break agreement.

What we know

  • ๐Ÿ“ WhereUnincorporated Haskell County, Haskell County
  • ๐Ÿข CompanyHaskell DC Owner, LLC (c/o Crusoe)
  • ๐Ÿ›๏ธ Owned byCrusoe
  • ๐ŸŒณ Size2,042 acres
  • ๐Ÿ’ต Cost$1 billion
  • ๐Ÿ’ธ Tax breaks10-year county property tax break per phase. Instead, the company pays the larger of $10 million a year or 25% of the county taxes it would owe. It must create at least 50 full-time jobs or pay more.
  • ๐Ÿ‘ท Jobs promised50

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 28, 2026
    Haskell County Commissioners Court created the 'Haskell County Crusoe RZ 2026' tax zone.
  • June 23, 2026
    County and Haskell DC Owner LLC signed the tax break agreement.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Tax Abatement Agreement between Haskell County and Haskell DC Owner, LLC ยท Haskell County ยท June 23, 2026

See something wrong? Tell us and we'll fix it.