Being builtBig (AI-size): 840 megawatts

Google Meitner Energy Center data center (near Pampa)

Also called: Meitner Energy Center, Project Pumpkin

Google and its energy partner Intersect are building a $3 billion data center near Pampa with its own wind, solar, batteries and some gas power. Plans show three buildings of about 750,000 square feet each, and filings describe up to 840 megawatts of data center power use on site. About 650 construction workers are on site.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Gray County Commissioners Court (for land outside city and town limits).

Where things stand: Being built Construction started in June 2026. Local leaders expect it to finish in late 2028 or early 2029.

❓ 3 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (June 4, 2026): Google and Intersect announced the Meitner Energy Center and started building. An 800-acre worker camp for up to 3,500 workers is planned in Wheeler County.

What we know

  • 📍 Where8810-8850 County Road 21 (Miami mailing address), Gray County, Unincorporated Gray County, Gray County
  • 🏢 CompanyIntersect (with Google)
  • 🏛️ Owned byGoogle (Alphabet)
  • 👤 Built forGoogle
  • ⚡ Power it needs840 megawatts (about as much as 672,000 homes)
  • 🔌 Where the power comes fromMore than 1 gigawatt of wind, solar and batteries built next to the data center, plus some gas power on site.
  • ❄️ CoolingAir cooling; water use limited to things like restrooms
  • 💵 Cost$3 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Did Gray County or Pampa give tax breaks? 🙋 I'll find out ·
  • How much gas power will be built on site? 🙋 I'll find out ·
  • How many permanent jobs will there be? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: exact site found in state records or maps.

    What happened so far

    • June 4, 2026
      Google and Intersect announced the Meitner Energy Center and started building. An 800-acre worker camp for up to 3,500 workers is planned in Wheeler County.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something