Digital Realty Garland campus expansion (Ferris Road / W. Campbell Road)
Also called: Digital Garland DFW37
Digital Realty is adding a $120 million data center building with 48 megawatts of space in Garland and plans up to four more with city tax breaks. Wells Fargo is a customer.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Garland City.
Where things stand: Being built DFW37 building under construction Mar. 2025 to Oct. 2026; up to four more buildings got city tax breaks.
❓ 2 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (March 2025): Construction of DFW37 (410,000 sq ft, six 8 MW halls, $120 million) was set to begin.
What we know
- 📍 Where1502 and 1505 Ferris Road and 1702 W. Campbell Road, Garland, Dallas County
- 🏢 CompanyDigital Realty
- 👤 Built forWells Fargo (one customer)
- ⚡ Power it needs48 megawatts (about as much as 38,400 homes)
- 💵 Cost$120 million
- 💸 Tax breaksGarland City Council granted tax breaks for up to four more data center buildings.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power will the full campus use? 🙋 I'll find out ·
- How much water? 🙋 I'll find out ·
🔎 What we checked
- Oct 7, 2026: We checked the site location: exact address found.
What happened so far
- March 2025Construction of DFW37 (410,000 sq ft, six 8 MW halls, $120 million) was set to begin.
Drag the slider to compare the land before and now.
Where this comes from
- Digital Realty files to expand planned data center campus in Garland, Texas · DatacenterDynamics · 2025
- Census geocoder match for 1502 Ferris Rd, Garland, TX · U.S. Census Bureau · Oct 7, 2026