Send us a tip
Being builtBig (AI-size): 760 megawatts

CyrusOne campus at Freestone Energy Center (near Fairfield)

CyrusOne is building three large data center buildings next to a gas power plant near Fairfield. The plant would supply up to 760 megawatts. The $1.5 billion campus should be done by late 2027.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Freestone County Commissioners Court (for land outside city and town limits).

Where things stand: Being built Two of three buildings under construction; campus to finish by end of Aug. 2027.

❓ 4 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (2026): State building filings for three buildings (about 918,650 sq ft, $1.5 billion) were reported.

What we know

  • 📍 WhereFM 488 near Fairfield, next to Calpine's Freestone gas power plant, Unincorporated Freestone County, Freestone County
  • 🏢 CompanyCyrusOne
  • 🏛️ Owned byKKR and Global Infrastructure Partners
  • ⚡ Power it needs760 megawatts (about as much as 608,000 homes)
  • 🔌 Where the power comes fromNext to the 1-gigawatt Freestone natural gas power plant run by Calpine (owned by Constellation).
  • 💵 Cost$1.5 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the site inside Fairfield city limits or unincorporated Freestone County? 🙋 I'll find out ·
  • How much water will it use? 🙋 I'll find out ·
  • Did Freestone County give a tax break? 🙋 I'll find out ·
  • Who is the tenant? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: approximate location found.

    What happened so far

    • 2026
      CyrusOne broke ground on the campus.
    • 2026
      State building filings for three buildings (about 918,650 sq ft, $1.5 billion) were reported.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. CyrusOne breaks ground on 380MW data center in Texas · DatacenterDynamics · 2026
    2. CyrusOne files to develop three buildings for $1.5bn data center campus in Fairfield, Texas · DatacenterDynamics · 2026
    3. Census geocoder match for 1366 FM 488, Fairfield, TX 75840 · U.S. Census Bureau · Oct 7, 2026