Proposed
Sangha Renewables Project Genesis data center (solar-powered)
Also called: Project Genesis
Sangha Renewables plans a data center beside a solar farm in Ector County for AI and cloud work. It has about 20 megawatts of power now and wants to grow to about 110 megawatts, mostly by 2028.
Where things stand: About 20 megawatts of power is available now. The state grid operator (ERCOT) gave a conditional OK in 2026 to grow to about 110 megawatts, with more power expected in May 2028.
๐ Latest update (Sept 2026): ERCOT, the state grid operator, gave the 110-megawatt campus a conditional 'base load' OK in its Batch Zero review.
What we know
- ๐ WhereNext to a large solar farm in Ector County (exact site not published in sources we opened), Unincorporated Ector County, Ector County
- ๐ข CompanySangha Renewables
- ๐ค Built forunknown (AI, cloud and computing work planned)
- โก Power it needs110 megawatts (about as much as 88,000 homes)
- ๐ Where the power comes fromA utility-scale solar farm being built alongside it in Ector County, plus the grid
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where exactly is the site? ๐ I'll find out
- Is any part of it running now, and for what (AI or bitcoin mining)? ๐ I'll find out
- How much water will it use? ๐ I'll find out
What happened so far
- 2025Sangha Renewables announced Project Genesis, a data center campus beside a solar farm in Ector County.
- Sept 2026ERCOT, the state grid operator, gave the 110-megawatt campus a conditional 'base load' OK in its Batch Zero review.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Sangha Renewables advances Texas data center project after ERCOT grid review ยท W.Media ยท Sept 2026