ProposedBig (AI-size): 3,700 acres

Google Project Roman data center (near Hereford)

Also called: Roman Project, IP Roman III Gas

Google and Intersect plan a large data center on 3,700 acres northwest of Hereford, with its own gas power plant and wind and solar farms. Farmers worry about water. The developers say they will use the Santa Rosa Aquifer, not the Ogallala.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Deaf Smith County Commissioners Court (for land outside city and town limits).

Where things stand: Proposed Early stage. Land is bought, a gas plant air permit was requested, and tax breaks were being discussed in July 2026.

❓ 4 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Aug 27, 2026): Reporting said the project has four phases, with 3,700 acres for the first phase and more land for solar and wind.

What we know

  • 📍 WhereAbout 13 to 20 miles northwest of Hereford, Unincorporated Deaf Smith County, Deaf Smith County
  • 🏢 CompanyIntersect (with Google)
  • 🏛️ Owned byGoogle (Alphabet)
  • 👤 Built forGoogle
  • 🌳 Size3,700 acres
  • 🔌 Where the power comes fromIts own gas power plant, plus planned wind and solar farms
  • 💧 WaterSanta Rosa Aquifer (not the Ogallala), per developers at a public meeting
  • 💸 Tax breaksA tax break was proposed. The Deaf Smith County Hospital District board was set to consider it on July 23, 2026.
  • 👷 Jobs promised90

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will the data center use? 🙋 I'll find out ·
  • How much water will it pump from the Santa Rosa Aquifer each day? 🙋 I'll find out ·
  • Did the county and hospital district approve tax breaks, and on what terms? 🙋 I'll find out ·
  • Will there be a contested hearing on the gas plant air permit? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 15, 2026
      Developers held a public information meeting in Hereford. They said about 2,500 construction jobs and 90 permanent jobs.
    • July 24, 2026
      Public comment deadline at TCEQ for the gas plant air permit (permit 184403).
    • Aug 27, 2026
      Reporting said the project has four phases, with 3,700 acres for the first phase and more land for solar and wind.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Community members seek answers at Hereford meeting on proposed Google data center · NewsChannel 10 (KFDA) · July 15, 2026