Built & running
IREN Childress campus (bitcoin mine becoming AI data center for Microsoft)
Also called: Horizon 1, IREN Childress Horizon
IREN runs a large bitcoin mining campus at Childress and is adding liquid-cooled AI halls for Microsoft. The first AI hall opened in August 2026, and three more are planned.
Where things stand: First 50-megawatt AI hall (Horizon 1) was handed to Microsoft in August 2026. More halls are planned in 2026.
๐ Latest update (Aug 13, 2026): IREN said its first 50-megawatt liquid-cooled AI hall at Childress (Horizon 1) was delivered to and accepted by Microsoft.
What we know
- ๐ WhereIREN's campus at Childress (exact site and city-limits status not confirmed in sources we opened), Unincorporated Childress County, Childress County
- ๐ข CompanyIREN Limited
- ๐ค Built forMicrosoft (AI cloud contract worth $9.7 billion over five years)
- โก Power it needs750 megawatts (about as much as 600,000 homes)
- โ๏ธ CoolingDirect-to-chip liquid cooling in the new AI halls
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water do the new AI halls use? ๐ I'll find out
- Did Childress County give a tax break? ๐ I'll find out
- Is the site inside Childress city limits? ๐ I'll find out
What happened so far
- Nov 2025IREN signed a $9.7 billion, five-year AI cloud contract with Microsoft.
- Aug 13, 2026IREN said its first 50-megawatt liquid-cooled AI hall at Childress (Horizon 1) was delivered to and accepted by Microsoft.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- IREN delivers Horizon 1 to Microsoft and achieves NVIDIA Exemplar Cloud status on GB300 NVL72 ยท IREN (GlobeNewswire) ยท Aug 13, 2026
See something wrong? Tell us and we'll fix it.