Built & running

IREN Childress campus (bitcoin mine becoming AI data center for Microsoft)

Also called: Horizon 1, IREN Childress Horizon

IREN runs a large bitcoin mining campus at Childress and is adding liquid-cooled AI halls for Microsoft. The first AI hall opened in August 2026, and three more are planned.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 6, 2026

Where things stand: First 50-megawatt AI hall (Horizon 1) was handed to Microsoft in August 2026. More halls are planned in 2026.

๐Ÿ•’ Latest update (Aug 13, 2026): IREN said its first 50-megawatt liquid-cooled AI hall at Childress (Horizon 1) was delivered to and accepted by Microsoft.

What we know

  • ๐Ÿ“ WhereIREN's campus at Childress (exact site and city-limits status not confirmed in sources we opened), Unincorporated Childress County, Childress County
  • ๐Ÿข CompanyIREN Limited
  • ๐Ÿ‘ค Built forMicrosoft (AI cloud contract worth $9.7 billion over five years)
  • โšก Power it needs750 megawatts (about as much as 600,000 homes)
  • โ„๏ธ CoolingDirect-to-chip liquid cooling in the new AI halls

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Nov 2025
    IREN signed a $9.7 billion, five-year AI cloud contract with Microsoft.
  • Aug 13, 2026
    IREN said its first 50-megawatt liquid-cooled AI hall at Childress (Horizon 1) was delivered to and accepted by Microsoft.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. IREN delivers Horizon 1 to Microsoft and achieves NVIDIA Exemplar Cloud status on GB300 NVL72 ยท IREN (GlobeNewswire) ยท Aug 13, 2026

See something wrong? Tell us and we'll fix it.