A $700 million data center planned on Texas A&M's RELLIS campus in Bryan stalled when its first developer went bankrupt. A new company, ThisWay Global, took over in 2026 with approval from A&M, Bryan and the county.
Where things stand: Delayed after the first developer lost backing; a new owner took over in Aug. 2026.
๐ Latest update (Aug 18, 2026): Brazos County commissioners voted 4-0 to move the tax deal to the new owner, ThisWay Global.
What we know
- ๐ WhereTexas A&M University System RELLIS Campus, Bryan, Brazos County
- ๐ข CompanyThisWay Global, Inc. (took over from RELLIS LLC group)
- ๐ต Cost$700 million
- ๐ธ Tax breaksCounty gets taxes on 50% of the value for 10 years, then 100% for 30 years (40-year deal). Land is A&M-owned.
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- When will construction start? ๐ I'll find out
- How much power and water will it use? ๐ I'll find out
- Who will use it? ๐ I'll find out
What happened so far
- Aug 18, 2026Brazos County commissioners voted 4-0 to move the tax deal to the new owner, ThisWay Global.
Local votes and rules
๐ค Agreement with the company
Brazos County commissioners voted 4-0 to move the tax break deal for a $700 million data center on Texas A&M's RELLIS campus in Bryan to a new company, ThisWay Global, after the first developer went bankrupt. The deal runs 40 years: the county taxes 50% of the property value for the first 10 years and 100% after that. Texas A&M regents and the City of Bryan approved similar transfers earlier.
Drag the slider to compare the land before and now.
Where this comes from
- Brazos County commissioners approve new owner for RELLIS data center ยท KBTX ยท Aug 18, 2026
- Brazos County could vote on new ownership for delayed $700 million RELLIS data center ยท KBTX ยท Aug 18, 2026
See something wrong? Tell us and we'll fix it.