Viridien computing center (Longwood Drive, Brenham)
French tech company Viridien plans a $100 million computing center on 21 acres in Brenham, growing to three buildings and 45 megawatts by 2028. The city refused a tax break after many residents objected. The city says it is for the company's own research, not AI or crypto.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Brenham City.
Where things stand: Proposed City Council unanimously denied a tax break zone on Jan. 8, 2026; company says it still plans to build.
❓ 2 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (Jan 8, 2026): Brenham City Council unanimously rejected a reinvestment zone for the project.
What we know
- 📍 Where2602 Longwood Drive, Brenham, Washington County
- 🏢 CompanyViridien (formerly CGG)
- 🌳 Size21 acres
- ⚡ Power it needs45 megawatts (about as much as 36,000 homes)
- 🔌 Where the power comes fromBluebonnet Electric Cooperative; company says it will pay for its own power hookups.
- ❄️ CoolingImmersion cooling (computers sit in special liquid).
- 💵 Cost$100 million
- 💸 Tax breaksCity Council denied a reinvestment zone and tax phase-in.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has building started? 🙋 I'll find out ·
- How much water will it use? 🙋 I'll find out ·
🔎 What we checked
- Oct 7, 2026: We checked the site location: exact address found.
What happened so far
- Jan 8, 2026Brenham City Council unanimously rejected a reinvestment zone for the project.
Drag the slider to compare the land before and now.
Where this comes from
- Officials in Brenham, Texas, reject tax abatement for data center project · DatacenterDynamics · Jan 2026
- Brenham City Council rejects reinvestment zone for tech project · KWHI · Jan 8, 2026
- Texas StratMap address point: 2602 LONGWOOD DRIVE (Washington County) · Texas Geographic Information Office (TxGIO) · Oct 7, 2026
See something wrong? Tell us and we'll fix it.