ProposedBig (AI-size): 500 acres
Project Big Pine (TexAmericas Center)
TexAmericas Center and Potentia Development plan a 500-acre campus for data centers near Texarkana. They estimate $3.5 billion in investment and say at least six companies are interested.
What happens next?
🗓️ No meeting or deadline known yet.
Where things stand: Proposed Site developer says it is in active planning; aims to have power in 24-30 months.
❓ 3 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (April 28, 2026): TexAmericas Center and Potentia announced they are moving forward with a 500-acre campus.
What we know
- 📍 WhereTexAmericas Center (former Red River Army Depot area), unknown, Bowie County
- 🏢 CompanyPotentia Development with TexAmericas Center
- 🌳 Size500 acres
- 🔌 Where the power comes fromWould not use the regular grid; batteries, gas and other on-site power are being studied. A 345-kV power line is nearby.
- 💵 Cost$3.5 billion
- 👷 Jobs promised120
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which company would build a data center here? 🙋 I'll find out ·
- What kind of on-site power plant would be used? 🙋 I'll find out ·
- How much water would it use? 🙋 I'll find out ·
What happened so far
- April 28, 2026TexAmericas Center and Potentia announced they are moving forward with a 500-acre campus.
🛰️ See it from above
Drag the slider to compare the land before and now.
20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- TexAmericas Center moving forward with potential data center site · KSLA · April 28, 2026
- TexAmericas Center Advances Rail-Served Data Center Site Project · Railway Age · April 2026
See something wrong? Tell us and we'll fix it.