Being builtBig (AI-size): 128 megawatts

Vantage TX1 data center campus, TX11 and TX12 (Texas Research Park)

Also called: TX11, TX12, Vantage TX1 campus

Vantage Data Centers bought about 58 acres on Omicron Drive at the Texas Research Park in 2023. It filed state plans for TX11, a 32-megawatt building, and then TX12, a $277 million, 96-megawatt building due in 2027. Environmental groups have threatened to sue over the on-site gas power planned for TX12.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Bexar County Commissioners Court (for land outside city and town limits).

Where things stand: Being built TX11 (32 MW) was due online in early 2026; TX12 (96 MW) is being built, due August 2027.

❓ 4 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (July 2026): Environmental groups (Environmental Integrity Project, Sierra Club, Public Citizen) sent a notice of intent to sue Vantage and VoltaGrid over gas power plants at two planned off-grid San Antonio-area data centers, including TX12.

What we know

  • 📍 Where14720 and 17420 Omicron Drive, Texas Research Park, west of Loop 1604 (outside San Antonio city limits), Unincorporated Bexar County, Bexar County
  • 🏢 CompanyVantage Data Centers
  • 🌳 Size58 acres
  • ⚡ Power it needs128 megawatts (about as much as 102,400 homes)
  • 🔌 Where the power comes fromTX12 is expected to use on-site natural gas generation from VoltaGrid. Groups say Vantage's two planned San Antonio-area off-grid sites together have gas plants of 423 MW and 151 diesel backup generators, with only 'minor source' air permits.
  • 💵 Cost$373 million

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the environmental groups file their Clean Air Act lawsuit, and what happens to the air permits? 🙋 I'll find out ·
  • Who are the tenants? 🙋 I'll find out ·
  • How much water will the campus use? 🙋 I'll find out ·
  • Were any tax breaks given? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 2023
      Vantage bought 57.9 acres at Texas Research Park from the University of Texas System.
    • Dec 15, 2023
      Work on TX11 began, according to a state building filing.
    • Sept 2025
      Vantage filed state plans for TX12, a $276.8 million building with up to 96 megawatts.
    • July 2026
      Environmental groups (Environmental Integrity Project, Sierra Club, Public Citizen) sent a notice of intent to sue Vantage and VoltaGrid over gas power plants at two planned off-grid San Antonio-area data centers, including TX12.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Denver data center company buys 89 acres on far West Side · San Antonio Report · Aug 31, 2023
    2. Vantage files plans for San Antonio data center · DatacenterDynamics · Dec 19, 2023
    3. Vantage files to build second San Antonio data center in Texas · DatacenterDynamics · Sept 23, 2025
    4. Vantage, VoltaGrid face lawsuit concerning natural gas powered off-grid data centers in San Antonio, Texas · DatacenterDynamics · July 24, 2026