Proposed
QTS San Antonio III data center site (Omicron subdivision)
Also called: QTS San Antonio III
QTS asked the San Antonio Planning Commission in 2023 to split a 48-acre tract near Highway 211 and Potranco Road for a future data center, next to Microsoft's campus. No building filing was found yet.
Where things stand: Land split approved for a data center site in 2023; no building plans found.
๐ Latest update (May 10, 2023): San Antonio Planning Commission considered QTS's request to create the Omicron Subdivision; staff recommended approval.
What we know
- ๐ WhereSouthwest of State Highway 211 and Potranco Road, Unincorporated Bexar County, Bexar County
- ๐ข CompanyQTS San Antonio III, LLC
- ๐๏ธ Owned byQTS (Blackstone)
- ๐ณ Size48 acres
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has QTS filed building plans? ๐ I'll find out
- How much power will it use? ๐ I'll find out
What happened so far
- May 10, 2023San Antonio Planning Commission considered QTS's request to create the Omicron Subdivision; staff recommended approval.
๐ฐ๏ธ See it from above
An aerial photo of the area.
Photos: USGS The National Map.
Where this comes from
- QTS files to subdivide land in San Antonio, Texas ยท DatacenterDynamics ยท May 18, 2023
- Texas data centers map and list ยท Cleanview (tracker) ยท Oct 2026