Being built

CleanSpark AI data center campus (Austin County)

Bitcoin miner CleanSpark is building an AI data center campus on 271 acres in Austin County, between Houston and Austin. It plans to turn on more than 200 megawatts in 2027.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 6, 2026

Where things stand: Substation work under way; over 200 MW to get power in first half of 2027.

๐Ÿ•’ Latest update (Oct 29, 2025): CleanSpark announced it bought rights to 271 acres and signed 285 MW of power deals.

What we know

  • ๐Ÿ“ Whereunknown, Austin County
  • ๐Ÿข CompanyCleanSpark
  • ๐ŸŒณ Size271 acres
  • โšก Power it needs285 megawatts (about as much as 228,000 homes)
  • ๐Ÿ”Œ Where the power comes fromLong-term power deals for 285 MW; site is near gas pipelines that could feed on-site power plants.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Oct 29, 2025
    CleanSpark announced it bought rights to 271 acres and signed 285 MW of power deals.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

RecentRecent
Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. CleanSpark Acquires Land and Power in Texas for AI Data Center Push Beyond Bitcoin ยท The Energy Mag ยท Oct 29, 2025
  2. CleanSpark acquires 447 acres for second Texas AI data center site ยท DatacenterDynamics

See something wrong? Tell us and we'll fix it.