ProposedBig (AI-size): 218 megawatts

Wyalusing Energy Center / Klondike data center (Bradford County)

Also called: KDI Wyalusing Power LLC, Klondike Digital Infrastructure, Wyalusing Energy Center (Klondike Digital Infrastructure)

A company plans a data center powered by its own gas power plant near Wyalusing in Bradford County, about 218 megawatts. An air permit for the power plant was reported issued. Exact municipality not confirmed.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Wyalusing Township.

Where things stand: Proposed PA DEP issued the air permit (plan approval 08-00060A) for the on-site gas power plant on Oct. 9, 2025. Bradford County adopted data center rules in 2026.

❓ 2 open questions about it: see below.

Last checked Oct 12, 2026.

🕒 Latest update (Oct 9, 2025): DEP issued the air permit (plan approval 08-00060A) for the power plant.

What we know

  • 📍 WhereWyalusing Township, Bradford County
  • 🏢 CompanyKDI Wyalusing Power LLC
  • 🏛️ Owned byKlondike Digital Infrastructure / New Fortress Energy (reported)
  • ⚡ Power it needs218 megawatts (about as much as 174,400 homes)
  • 🔌 Where the power comes fromOn-site gas power plant (Wyalusing Energy Center): eight GE TM2500 gas turbines, up to 218 megawatts

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will the power plant and data center use? Has SRBC approved it? 🙋 I'll find out ·
  • Who is the end user? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

    What happened so far

    • Dec 26, 2024
      KDI Wyalusing Power applied to DEP for an air permit for an on-site gas power plant to run a data center.
    • Oct 9, 2025
      DEP issued the air permit (plan approval 08-00060A) for the power plant.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Bradford County adopts data center rules; Wyalusing hyperscale project's air permit issued · NorthcentralPA.com
    2. Wyalusing Energy Center / Klondike Wyalusing Data Center · More Than Just Parks Data Center Tracker · July 9, 2026
    3. PA Data Center Permit Tracker - all projects list (CSV behind the DEP map) · Pennsylvania DEP · Oct 6, 2026
    4. Northcentral Regional Office community information (KDI Wyalusing Power, 08-00060A) · Pennsylvania DEP · Oct 9, 2025
    5. KDI Wyalusing Power LLC (New Fortress) 08-00060A Proposed Plan Approval · Pennsylvania DEP · June 30, 2025
    6. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
    7. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
    8. PA DEP Data Center Permit Tracker (lists Wyalusing Township) · Pennsylvania DEP · Oct 6, 2026

    See something wrong? Tell us and we'll fix it.