Send us a tip
Status unclearBig (AI-size): 120 megawatts

Project Trainer (Ridge Road, Trainer Borough)

Also called: Link Logistics

The owner of a 24-acre site in Trainer asked the borough whether a 120-megawatt data center would be allowed. It says no decision has been made to build.

👥 Reported, not confirmed yetSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Thursday, December 10, 2026 (time not announced)

Trainer Borough Council meeting

📍 Trainer Municipal Building, 4300 Township Line Road, Trainer, PA 19061. Council meets the second Thursday of each month; the borough code says 7:30 p.m., but check the time with the borough.

Regular meeting (second Thursday). No agenda seen.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Status unclear Owner's lawyer asked for a zoning determination in Aug. 2026; says no formal application and still in 'due diligence'.

❓ 2 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Aug 2026): Lawyer requested a preliminary zoning determination for a 'proposed data center'.

What we know

  • 📍 Where4401 Ridge Road (listed by Link Logistics as Juniper Pointe Logistics Center), Trainer, Delaware County
  • 🏢 CompanyLink Logistics
  • 🏛️ Owned byBlackstone
  • 🌳 Size24 acres
  • ⚡ Power it needs120 megawatts (about as much as 96,000 homes)
  • 🔌 Where the power comes fromLikely a 3-acre substation and backup gas or diesel generators
  • ❄️ CoolingClosed-loop; no process water needed (lawyer's letter)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has PECO received a request for power service? 🙋 I'll find out ·
  • Will a formal application be filed? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Delaware River Basin Commission's (DRBC) list of pending applications (August 2026): there is no application for this data center. DRBC said in November 2025 it had not received any data center applications. A data center needs its own DRBC approval only if it takes more than 100,000 gallons a day from its own wells or streams, or discharges more than 50,000 gallons a day (lower limits in some protected areas). Buying water from a water company does not need a separate DRBC approval.
    • Oct 12, 2026: We checked the official agenda for the Oct. 8 borough council meeting: it had no data center item.

    What happened so far

    • Aug 2026
      Lawyer requested a preliminary zoning determination for a 'proposed data center'.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Delco data center: What we know about possible proposal · WHYY · Sept 23, 2026
    2. Trainer Council Meeting (PA Data Center Hearings and Meetings calendar) · Luma community calendar · Oct 6, 2026
    3. Frequently Asked Questions: Data Centers · Delaware River Basin Commission · Nov 24, 2025
    4. DRBC Project Review: Pending Project Status (August 2026) · Delaware River Basin Commission · Aug 2026
    5. 4401 Ridge Road build-to-suit listing · Link Logistics · Oct 7, 2026
    6. U.S. Census Geocoder result for 4401 Ridge Rd, Marcus Hook, PA 19061 · U.S. Census Bureau · Oct 7, 2026
    7. Agenda, Trainer Borough Council Meeting, October 8, 2026 · Borough of Trainer · Oct 2026
    8. Chapter 14: Borough Council (meeting schedule) · Borough of Trainer (eCode360)

    See something wrong? Tell us and we'll fix it.