ProposedBig (AI-size): 200 megawatts

Alpha Compute data center campus (Tioga County)

Alpha Compute said it would buy land and natural gas rights in Tioga County for a data center campus of about 200 megawatts. The exact town has not been confirmed.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Where things stand: Proposed Company signed a binding term sheet (Aug. 11, 2026) to buy land and gas rights for $55 million. Deal is not closed and needs county and state approvals.

❓ 3 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Aug 11, 2026): Alpha Compute announced a binding term sheet to buy land and gas rights for $55 million for a 200 megawatt campus that could grow to 1,000 megawatts, powered by gas from the property.

What we know

  • 📍 Whereunknown, Tioga County
  • 🏢 CompanyAlpha Compute Corp.
  • 🌳 Size350 acres
  • ⚡ Power it needs200 megawatts (about as much as 160,000 homes)
  • 🔌 Where the power comes fromGas from rights bought with the land (on-site gas power likely)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

    What happened so far

    • Aug 11, 2026
      Alpha Compute announced a binding term sheet to buy land and gas rights for $55 million for a 200 megawatt campus that could grow to 1,000 megawatts, powered by gas from the property.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Exclusive: Alpha Compute to buy Pennsylvania land, gas rights for $55 million data center campus · Reuters (via Investing.com)
    2. Alpha Compute Tioga County Data Center Campus · More Than Just Parks Data Center Tracker
    3. Alpha Compute signs binding term sheet for planned 200 MW natural gas powered data center campus in Pennsylvania with potential expansion to 1 GW · Alpha Compute Corp. press release (GlobeNewswire) · Aug 11, 2026
    4. Alpha Compute plans Pennsylvania AI campus · BIC Magazine · 2026
    5. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
    6. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026

    See something wrong? Tell us and we'll fix it.