Proposed

Alpha Compute data center campus (Tioga County)

Alpha Compute said it would buy land and natural gas rights in Tioga County for a data center campus of about 200 megawatts. The exact town has not been confirmed.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Company signed a binding term sheet (Aug. 11, 2026) to buy land and gas rights for $55 million. Deal is not closed and needs county and state approvals.

๐Ÿ•’ Latest update (Aug 11, 2026): Alpha Compute announced a binding term sheet to buy land and gas rights for $55 million for a 200 megawatt campus that could grow to 1,000 megawatts, powered by gas from the property.

What we know

  • ๐Ÿ“ Whereunknown, Tioga County
  • ๐Ÿข CompanyAlpha Compute Corp.
  • ๐ŸŒณ Size350 acres
  • โšก Power it needs200 megawatts (about as much as 160,000 homes)
  • ๐Ÿ”Œ Where the power comes fromGas from rights bought with the land (on-site gas power likely)

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

๐Ÿ”Ž What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

What happened so far

  • Aug 11, 2026
    Alpha Compute announced a binding term sheet to buy land and gas rights for $55 million for a 200 megawatt campus that could grow to 1,000 megawatts, powered by gas from the property.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

2018โ€“20202021โ€“2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Exclusive: Alpha Compute to buy Pennsylvania land, gas rights for $55 million data center campus ยท Reuters (via Investing.com)
  2. Alpha Compute Tioga County Data Center Campus ยท More Than Just Parks Data Center Tracker
  3. Alpha Compute signs binding term sheet for planned 200 MW natural gas powered data center campus in Pennsylvania with potential expansion to 1 GW ยท Alpha Compute Corp. press release (GlobeNewswire) ยท Aug 11, 2026
  4. Alpha Compute plans Pennsylvania AI campus ยท BIC Magazine ยท 2026
  5. Water Use by Data Centers in the Susquehanna River Basin - FAQ ยท Susquehanna River Basin Commission ยท 2026
  6. Water Application and Approval Viewer (WAAV) ยท Susquehanna River Basin Commission ยท Oct 6, 2026

See something wrong? Tell us and we'll fix it.