Terawatt data center proposal at former Appvion paper mill
Also called: Terawatt Roaring Spring Data Center
A company called Terawatt wants to build a data center at the old Appvion paper mill near Roaring Spring. Taylor Township is writing rules for data centers first. Neighbors worry about noise near a school, YMCA and ball fields.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Taylor Township.
Where things stand: Proposed The township held a public hearing on Oct. 8, 2026 on new data center rules. No vote yet, and no application from Terawatt.
- Oct 22, 2026: Taylor Township, Blair County: data center rules (ordinance) adopted Source
❓ 5 open questions about it: see below.
Last checked Nov 9, 2026.
🕒 Latest update (Oct 22, 2026): Taylor Township supervisors voted 3-0 at a special meeting to add data center rules to the township's land development ordinance. The rules set a 300-foot setback from property lines and roads and require large power users to pay their full power line and generation costs.
What we know
- 📍 WhereFormer Appvion paper mill and nearby woods, near Roaring Spring, Taylor, Blair County
- 🏢 CompanyTerawatt
- 🔌 Where the power comes fromCompany would get its own power; residents worry about Penelec grid capacity
- 🤐 Privacy agreement (NDA)No
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How big would the data center be and how much power would it use? 🙋 I'll find out ·
- Would it build its own gas power plant? 🙋 I'll find out ·
- Where would its water come from, and who gets water first in a drought? 🙋 I'll find out ·
- What happened at the October 5, 2026 township meeting? 🙋 I'll find out ·
- When will Terawatt file a land development plan with Taylor Township? 🙋 I'll find out ·
🔎 What we checked
- Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.
What happened so far
- Sept 2026Residents quizzed Taylor Township supervisors about the plan, raising noise, health, water and power concerns. Solicitor is drafting rules for Blair County Planning Commission review.
- Sept 24, 2026Question-and-answer session planned at the Blair County Convention Center.
- Oct 5, 2026Next township meeting was set for 6 p.m.
- Oct 8, 2026About 200 people came to the township's public hearing on new data center rules (a change to the land development ordinance). All 23 speakers opposed the project, and a petition with about 2,300 signatures was handed in. No vote was taken.
- Oct 22, 2026Taylor Township supervisors voted 3-0 at a special meeting to add data center rules to the township's land development ordinance. The rules set a 300-foot setback from property lines and roads and require large power users to pay their full power line and generation costs.
Local votes and rules
📜 Data center rules
Taylor Township supervisors unanimously approved changes to the township's land development rules for data centers at a special meeting. Data centers must be at least 300 feet from existing buildings and keep sound at or below 50 decibels. Some residents said the setbacks are too short. The township says it has no plans from any developer.
📜 Data center rules
Taylor Township supervisors will consider a change to the township's land development rules for data centers on Oct. 8, 2026 at 6:30 p.m. at the Roaring Spring Fire Company. It follows a proposal for a data center at the old Appvion paper mill site.
Drag the slider to compare the land before and now.
Where this comes from
- Taylor Twp. supervisors quizzed on data center Appvion site proposal · Altoona Mirror · Sept 8, 2026
- Terawatt Roaring Spring Data Center · More Than Just Parks Data Center Tracker
- Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
- Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
- Data Center Town Hall Draws Nearly 250 · Morrisons Cove Herald · Oct 1, 2026
- Crowd objects to proposed Taylor Township data center · Altoona Mirror · Oct 8, 2026
- Taylor Township Reviews Proposed Data Center Site, Schedules SALDO Hearing · Morrisons Cove Herald · Oct 8, 2026
- Taylor Township Approves Data Center Ordinance · Morrisons Cove Herald · Oct 29, 2026
See something wrong? Tell us and we'll fix it.