Send us a tip
ProposedBig (AI-size): 830 acres

Nadara data center site near Gans (Fay-Penn land)

Also called: Nadara Fayette

A European power company, Nadara, has the right to buy about 800 acres near Gans from Fay-Penn, the county's economic development group, and is exploring a data center there. Springhill Township passed rules for data centers and power plants in September 2026. No plans have been filed.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Springhill Township.

Where things stand: Proposed Nadara has a right-to-purchase agreement with the Fay-Penn Economic Development Council for about 800 acres and is exploring a data center. Springhill Township adopted data center and power plant rules in September 2026.

❓ 4 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Sept 19, 2026): Supervisors unanimously adopted data center and power generation ordinances.

What we know

  • 📍 WhereAbout 800-830 acres near Gans, Springhill, Fayette County
  • 🏢 CompanyNadara (European independent power producer)
  • 🌳 Size830 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • What exactly does Nadara plan to build, and would it include a gas power plant? 🙋 I'll find out ·
  • What are the terms of Fay-Penn's purchase agreement with Nadara, and did Fay-Penn sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
  • Where would the water come from (Monongahela or Cheat River?) and how much per day? 🙋 I'll find out ·
  • Would new power lines be needed? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • June 5, 2026
      About 250 people came to a data center town hall at Penn State Fayette; Nadara was reported exploring an 830-acre site near Gans.
    • Sept 7, 2026
      Springhill Township adopted a noise and dust ordinance.
    • Sept 19, 2026
      Supervisors unanimously adopted data center and power generation ordinances.

    Local votes and rules

    📜 Data center rules

    Springhill Township supervisors unanimously adopted two ordinances: one setting rules for data centers and one for fossil fuel power plants that serve them. A noise and dust ordinance passed earlier in September. The township says it has received no applications.

    Sept 17, 2026

    ⏸️ Pause on new data centers

    Springhill Township supervisors put off votes on the data center and power plant rules so the public notice could run long enough. They passed a resolution saying no data center or power plant applications would be accepted until the September 17 vote. They did adopt a new noise and dust ordinance the same night.

    Sept 4, 2026

    📜 Data center rules

    Springhill Township introduced draft rules for data centers, plus rules on noise, dust, and fossil-fuel power plants. A power company has shown interest in an 800-acre site. A special meeting on the rules was set for September 3, 2026, with a final vote expected later.

    July 16, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    We only know the town, so this shows the town center, not the exact site. Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data center town hall draws large crowd in Fayette · Observer-Reporter · June 5, 2026
    2. Springhill Township adopts data center, power generation ordinances · Observer-Reporter · Sept 19, 2026