Proposed

York 2 Energy Center data center (Peach Bottom Township)

Also called: Calpine, Energy Capital Partners

In July 2025, Energy Capital Partners and its company Calpine announced a $5 billion data center at the York 2 gas power plant in Peach Bottom Township. Calpine has since been bought by Constellation Energy, which must sell the York 2 plant. It is not clear who will build the data center.

✔ ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Announced July 2025 at the Pennsylvania energy summit. No groundbreaking reported. The power plant must be sold as part of Constellation's purchase of Calpine.

🕒 Latest update (Jan 7, 2026): Constellation Energy finished buying Calpine. The Justice Department required it to sell the York 2 plant.

🗓️ Next meeting of the people who decide: Oct 7, 2026 · 7:00 PM
Peach Bottom Township Board of Supervisors. We don't know yet if York 2 Energy Center data center (Peach Bottom Township) is on the agenda. Call the office to check before you go.
📍 Peach Bottom Township Municipal Building; township office is 6880 Delta Road, Suite 3, Delta, PA 17314. Supervisors meet the 1st Wednesday of each month at 7 p.m.; Planning Commission the 3rd Tuesday at 7 p.m. (Oct. 20). The township has posted a draft data center ordinance.

What we know

  • 📍 WhereYork 2 Energy Center (gas power plant), near the Peach Bottom nuclear plant, Peach Bottom Township, York County
  • 🏢 CompanyCalpine (Energy Capital Partners)
  • 🏛️ Owned byCalpine is now owned by Constellation Energy (Jan. 2026), which must sell the York 2 plant under a U.S. Justice Department order
  • 🔌 Where the power comes fromNext to the York 2 Energy Center, an 828 megawatt gas power plant
  • 💵 Cost$5 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts and buildings? 🙋 I'll find out
  • How much water from the Susquehanna River? Has SRBC approved it? 🙋 I'll find out
  • Will the data center need its own water approval from the Susquehanna River Basin Commission, or will it share the power plant's river water? 🙋 I'll find out
  • Who will own the York 2 power plant after Constellation sells it, and is the data center plan still going ahead? 🙋 I'll find out

🔎 What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

What happened so far

  • July 15, 2025
    $5 billion data center at the York 2 Energy Center announced at the Pennsylvania Energy and Innovation Summit; 2,500 construction jobs promised.
  • Sept 24, 2025
    The Susquehanna River Basin Commission (SRBC) renewed and changed water approvals for Calpine's York Energy Center gas power plants: up to 19.01 million gallons a day can be taken from the Susquehanna River (Conowingo Pool) on the peak day, and up to 5.8 million (Block 2) and 4.9 million (Block 1) gallons a day can be used up (lost to evaporation) on the peak day. These approvals are for the power plants, not for the planned data center.
  • Jan 7, 2026
    Constellation Energy finished buying Calpine. The Justice Department required it to sell the York 2 plant.

Local votes and rules

📜 Data center rules

Peach Bottom Township posted a draft data center ordinance for review by the York County Planning Commission. No final vote had been taken, and the township planned public comment first. A large data center is planned at the York 2 Energy Center power plant site in the township.

May 21, 2026
🛰️ See it from above

Drag the slider to compare the land before and now.

2018–20202021–2023
We only know the town, so this shows the town center, not the exact site. Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Local officials are preparing for a wave of data centers in York County · York Dispatch · July 31, 2025
  2. $5B data center coming to York County energy site · Central Penn Business Journal
  3. Peach Bottom Township home page (Regular Meeting Schedule) · Peach Bottom Township · Oct 6, 2026
  4. SRBC: Actions Taken at the September 24, 2025 Meeting · Federal Register · Sept 29, 2025
  5. WAAV project details: Calpine Mid-Merit II, York Energy Center Block 2 (Approval 20250903) · Susquehanna River Basin Commission · Sept 24, 2025
  6. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
  7. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
  8. $5 billion data center planned in York County · abc27 · July 2025
  9. Constellation Energy completes Calpine acquisition · Industrial Info Resources · Jan 9, 2026

See something wrong? Tell us and we'll fix it.