Send us a tip
Approved, not built yetBig (AI-size): Described as an AI or hyperscale project in the sources

Iron City Wells AI data center with gas generators

Also called: Iron City No. 1 Power Generator and Compute Center

State regulators gave Iron City Wells an air permit to run 15 gas generators to power an AI data center in Karthaus Township. Few other details are public, such as its size or exact location.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Karthaus Township.

Where things stand: Approved, not built yet DEP issued an air permit (plan approval) in January 2026 for 15 gas-fired generators for an AI data center. Local status unknown.

❓ 5 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Jan 30, 2026): DEP issued an air quality plan approval for 15 gas generators at an 'A.I. data center' (about 51,759 tons of carbon dioxide-equivalent a year allowed).

What we know

  • 📍 WhereOff Paul Hoffman Road near Karthaus, on a gas well pad (OpenStreetMap lists 3160 Paul Hoffman Road), Karthaus, Clearfield County
  • 🏢 CompanyIron City Wells, LLC
  • 🔌 Where the power comes from15 natural gas-fired generators on site

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly is the site, and how many megawatts will it use? 🙋 I'll find out ·
  • Is it a new AI data center or a converted crypto mine? 🙋 I'll find out ·
  • Has Karthaus Township or Clearfield County approved it? 🙋 I'll find out ·
  • Where will water come from? 🙋 I'll find out ·
  • Is it already running? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.
    • Oct 8, 2026: We checked aerial photos: the map point is a cleared gas well pad in the woods off Paul Hoffman Road.

    What happened so far

    • Jan 30, 2026
      DEP issued an air quality plan approval for 15 gas generators at an 'A.I. data center' (about 51,759 tons of carbon dioxide-equivalent a year allowed).
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DEP issues air quality permit for 15 natural gas-fired generators for A.I. data center in Clearfield County · PA Environment Digest · Jan 30, 2026
    2. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
    3. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
    4. OpenStreetMap: Iron City No. 1 Power Generator and Compute Center · OpenStreetMap contributors · Oct 8, 2026
    5. Iron City No. 1 Power Generator and Compute Center · DC Hub · Oct 8, 2026
    6. Census geocoder: 3160 Paul Hoffman Rd, Karthaus · U.S. Census Bureau · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.