Project Hummingbird (former Robena Mine)
Also called: Project Hummingbird, IEP Greene County, Robena data center
A Pittsburgh power company plans to build a gas power plant at the old Robena Mine to attract a big data center. It would take up to 18 million gallons of water a day from the Monongahela River for power and cooling. The county approved the first phase of site work; no tenant has been named.
Where things stand: Greene County Planning Commission approved phase 1 site work (grading, two gas turbines, water plant) 8-1 in late 2025. No data center tenant announced.
๐ Latest update (Dec 19, 2025): Greene County Planning Commission voted 8-1 to approve phase 1: grading 309 acres, two gas turbines, and a water treatment plant.
What we know
- ๐ WhereFormer Robena Mine site along the Monongahela River, Monongahela, Greene County
- ๐ข CompanyInternational Electric Power (IEP), Pittsburgh
- ๐ค Built forunknown (developer said it was talking with seven possible customers)
- ๐ณ Size1,400 acres
- โก Power it needs910 megawatts (about as much as 728,000 homes)
- ๐ Where the power comes fromTwo gas turbines on site (910 megawatts), not relying on the grid day to day; backup connection to FirstEnergy and batteries
- ๐ง WaterMonongahela River, through a treatment plant built by Essential Utilities; public water from SPWA ยท 18,000,000 gallons a day
- โ๏ธ CoolingWater cooling (water treatment plant on site)
- ๐ท Jobs promised50
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has a data center tenant signed on? ๐ I'll find out
- Has DEP issued air and water permits for the gas turbines and water plant? ๐ I'll find out
- How much of the 18 million gallons a day will be lost to evaporation? ๐ I'll find out
- Will there be diesel backup generators? ๐ I'll find out
- Was a secret deal (NDA) signed with Monongahela Township or Greene County? ๐ I'll find out
- Will the project ask for a tax break? ๐ I'll find out
What happened so far
- Oct 16, 2025Project announced for the old Robena Mine.
- Oct 30, 2025Residents raised concerns at an open house.
- Nov 6, 2025County planners gave preliminary OK to development.
- Dec 19, 2025Greene County Planning Commission voted 8-1 to approve phase 1: grading 309 acres, two gas turbines, and a water treatment plant.
Drag the slider to compare the land before and now.
Where this comes from
- Greene County planners OK early work on proposed data center site ยท Herald-Standard / Greene County Messenger ยท Dec 19, 2025
- Development at Greene data center campus gets preliminary OK ยท Observer-Reporter ยท Nov 6, 2025
- Greene County Planning Commission document (Hummingbird land development) ยท Greene County
- IEP plans 944-MW behind-the-meter gas plant in Pennsylvania to power data center ยท Utility Dive
- PA DEP Data Center Permit Tracker ยท Pennsylvania DEP ยท Oct 6, 2026